Hearing Schedule
| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 21/04/2026 11:30 am | 2599/2025 |
Electro Solaire Pvt. Limited
Electro Solaire Pvt. Limited
|
GUVNL & Ors.
GUVNL & Ors.
|
Petition under Section 86(1)(f) of the Electricity Act, 2003 read with Electricity (Promotion of Generation of
Petition under Section 86(1)(f) of the Electricity Act, 2003 read with Electricity (Promotion of Generation of Electricity from Must-Run Power Plant) Rules, 2021 and the Power Purchase Agreement dated 26.08.2019.
|
__ |
| 2 | 21/04/2026 11:30 am | 2604/2026 |
DGVCL & Ors.
DGVCL & Ors.
|
TPL & Ors.
TPL & Ors.
|
Petition under Electricity Act, 2003 read with the GERC (Licensee’s Power to Recover Expenditure incurred in
Petition under Electricity Act, 2003 read with the GERC (Licensee’s Power to Recover Expenditure incurred in providing
supply and other Miscellaneous Charges) Regulations, 2005 for approval of levy of 2.5% supervision charges instead of
15% on the estimated cost towards erection of new Ring Main Unit (RMU), Compact Sub-Station (CSS), High Tension Metering Cubicle (HTMC), Vacuum Circuit Breaker (VCB), Resin Cast CTPT, Sandwich Busbar Trunking System and LT underground cable & its associated equipment, for LT/HT consumer/ applicant -laid/erected by the consumer/applicant as a special case.
|
__ |
| 3 | 21/04/2026 11:30 am | 2605/2026 |
M/s GSP Crop Science Private Limited
M/s GSP Crop Science Private Limited
|
GETCO & Ors.
GETCO & Ors.
|
Petition under Section 86 (1) (c) (e) & (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct o
Petition under Section 86 (1) (c) (e) & (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business)
Regulations, 2004 seeking directions for extension of time period for commissioning the entire evacuation infrastructure
along with commissioning of the project till 31.12.2026 due to occurrence of the unforeseen events and seeking extension of Period for commissioning the entire project under the “Tariff Framework for procurement of Power by Distribution
Licensees and Others from Solar Energy Projects and Other Commercial Issues for the State of Gujarat, 2024”, by invoking
inherent powers vested in the Hon'ble Commission for seeking extension.
|
__ |
| 4 | 21/04/2026 11:30 am | 2606/2026 |
M/s GSP Intermediates Private Limited
M/s GSP Intermediates Private Limited
|
GETCO & Ors.
GETCO & Ors.
|
Petition under Section 86 (1) (c) (e) & (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct o
Petition under Section 86 (1) (c) (e) & (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business)
Regulations, 2004 seeking directions for extension of time period for commissioning the entire evacuation infrastructure
along with commissioning of the project till 31.12.2026 due to occurrence of the unforeseen events and seeking extension of Period for commissioning the entire project under the “Tariff Framework for procurement of Power by Distribution
Licensees and Others from Solar Energy Projects and Other Commercial Issues for the State of Gujarat, 2024”, by invoking
inherent powers vested in the Hon'ble Commission for seeking extension.
|
__ |
| 5 | 21/04/2026 11:30 am | 2607/2026 |
V Grown Tech Pvt. Limited
V Grown Tech Pvt. Limited
|
GETCO
GETCO
|
Petition under Section 86 (1) (c), (e), (f) and other applicable provisions of EA, 2003 r/w. Clause 2.9 of the
Petition under Section 86 (1) (c), (e), (f) and other applicable provisions of EA, 2003 r/w. Clause 2.9 of the GERC’ Order No. 06/2024 dated 31.08.2024, seeking extension of Scheduled Date of Commissioning of infrastructure being developed by the Petitioner for 20 MW Solar Power Plant for captive use located at Village Nana Samdhiyala, Taluka Gir Gadhda, District Gir Somnath, to be evacuated to GETCO 66 KV Luvari Mori Substation on account of unforeseen reasons.
|
__ |
| 6 | 21/04/2026 11:30 am | 2611/2026 |
Samrath Diamond
Samrath Diamond
|
UGVCL
UGVCL
|
Petition under Section 86 (1) (f) and (e) of the Electricity Act, 2003 read with Regulations 80 and 82 of the
Petition under Section 86 (1) (f) and (e) of the Electricity Act, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations, 2004 to adjudicate upon the disputes between the licensees and generating company and for set-off of 4,47,649 units to be given by the Respondent UGVCL to the Petitioner in the future energy bill with regard to units injected into the Grid during the period from March 2025 to August 2025.
|
__ |
| 7 | 21/04/2026 11:30 am | 2615/2026 |
KEI Industries Limited
KEI Industries Limited
|
UGVCL & GETCO
UGVCL & GETCO
|
Petition under Sections 42, 43, 50, 86 & other applicable provisions of the Electricity Act, 2003 read with GE
Petition under Sections 42, 43, 50, 86 & other applicable provisions of the Electricity Act, 2003 read with GERC (Electricity Supply Code and Related Matters) Regulations, 2015, GERC (Standard of Performance of Distribution Licensee) Regulations 2023 and other applicable Regulations of GERC to declare that time period of 180 days as per Clause 4.2 of GERC (SoP) Regulations, 2023 read with Clause 4.33 of GERC Supply Code, 2015 be reckoned from the date of payment of final estimate issued by UGVCL and consequently directing UGVCL to refund the excess amount recovered from the Petitioner towards minimum demand charges considering deemed release of 4200 KVA Power Demand.
|
__ |
| 8 | 21/04/2026 11:30 am | 2617/2026 |
Gujarat Ambuja Export Limited (Dalpur Plant)
Gujarat Ambuja Export Limited (Dalpur Plant)
|
UGVCL
UGVCL
|
Petition under Sections (1) (e) and (f) and other applicable of EA, 2003 read with Regulation 11.2 of GERC Not
Petition under Sections (1) (e) and (f) and other applicable of EA, 2003 read with Regulation 11.2 of GERC Notification No. 5 of 2016, titled ‘Regulations for Net Metering Rooftop Solar PV Grid Interactive Systems’, alongwith its subsequent
amendments, and further read with the Interconnection Agreement (Provisional) executed between UGVCL and Solar PV
Project Owner dated 24.05.2021, seeking directions for execution of the final interconnection agreement, application of the relevant Regulations and prevailing amendments thereto at the time of commissioning, enforcement of the final agreement from the date of commissioning with the applicable tariff framework and refund of any differential amount, if any, alongwith the applicable interest.
|
__ |
| 9 | 21/04/2026 11:30 am | 2619/2026 |
Gujarat Ambuja Export Limited (Kadi Plant)
Gujarat Ambuja Export Limited (Kadi Plant)
|
UGVCL
UGVCL
|
Petition under Sections (1) (e) and (f) and other applicable of the Electricity Act, 2003 read with Regulation
Petition under Sections (1) (e) and (f) and other applicable of the Electricity Act, 2003 read with Regulation 11.2 of GERC Notification No. 5 of 2016, titled ‘Regulations for Net Metering Rooftop Solar PV Grid Interactive Systems’, alongwith its subsequent amendments, and further read with the Interconnection Agreement (Provisional) executed between the Respondent UGVCL and the Solar PV Project Owner at Kadi dated 29.05.2021, seeking directions for execution of the final interconnection agreement, application of the relevant Regulations and prevailing amendments thereto at the time of
commissioning, enforcement of the final agreement from the date of commissioning with the applicable tariff framework
and refund of any differential amount, if any, alongwith the applicable interest.
|
__ |