6:00 am

2565/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 (1) (b) (e), (f) and (i) of EA, 2003 read with Regulations for Net Metering Rooftop Solar PV Grid Interactive Systems’ Notification No. 5 of 2016 and its Subsequent amendments particularly the Third Amendments dated 31.05.2022 read with Inter connection (Provisional) Agreement between the Petitioner and the Respondents.

Find out more »

2566/2025 & IA No. 99/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 (1)(f) (c) & (e) and other applicable provisions of the Electricity Act, 2003 read with read with Regulations 80 & 82 of the GERC (Conduct of Business) Regulations, 2004 seeking extension of time period for construction of the evacuation infrastructure.

Find out more »

2567/2025 & IA No. 101/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 of EA, 2003 read with Order No. 01 of 2024 dated 22.02.2024 for ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial Issues for the State of Gujarat’ passed by the Commission, seeking extension of the Scheduled Date … Continue reading "2567/2025 & IA No. 101/2025"

Find out more »

2576/2025 & IAs No. 108/2025 & 109/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Sections 86 (1) (b), (e), (f) and (k) of the Electricity Act, 2003 read with Clause 3.5 of the “Tariff Framework for Procurement of Power by Distribution Licensees and Others from Solar Energy Projects and Other Commercial Issues for the State of Gujarat dated 08.05.2020 seeking inter-alia, extension of allocated evacuation infrastructure being … Continue reading "2576/2025 & IAs No. 108/2025 & 109/2025"

Find out more »

2577/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Sections 86 (1) (f) of the Electricity Act, 2003 read with Electricity (Promotion of Generation of Electricity from Must-Run Power Plant) Rules, 2021 and the PPA dated 26.08.2019.

Find out more »

2578/2025 & IAs No. 110/2025 & 113/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition filed under Section 86 (1) (a) read with Section 86 (1) (f) of the EA 2003 read with Article 8 of Power Purchase Agreement dated 14.12.2022 executed between the parties seeking extension of the Scheduled Commercial Operation Date (SCOD) due to various events of Force Majeure inter alia, on account of delays caused due … Continue reading "2578/2025 & IAs No. 110/2025 & 113/2025"

Find out more »

2596/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 of the Electricity Act, 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial Issues for the State of Gujarat’ and Final Order dated 11.11.2025 passed by the Commission … Continue reading "2596/2025"

Find out more »

2562/2025

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 (1) (f) of the Electricity Act, 2003 read with Articles 8 and 11 of the Power Purchase Agreement dated 10.05.2023 seeking extension of the timeline for Scheduled Commercial Operation Date on account of force majeure events viz. incessant rainfall causing flood like situation and cascading impacts and delay in grant of … Continue reading "2562/2025"

Find out more »

2571/2025 & IA No. 07/2026

April 9 @ 6:00 am - 11:30 am UTC+5.5

Petition filed under Section 86 (1) (f) of the Electricity Act, 2003 read with Article 8 of Power Purchase Agreement dated 10.05.2023 seeking extension of the timeline for the Scheduled Commercial Operation Date (SCOD) on account of Force Majeure events beyond the reasonable control of the Petitioner and consequential reliefs thereto.

Find out more »