In the matter of Petition under Section 86(1)(e), (f) and (k) of the Electricity act, 2003 read with Articles 8 & 11 of the Power Purchase Agreement dated 08.07.2020 executed between M/s Juniper Green Three Private Limited and Gujarat Urja Vikas Nigam Limited for supply of 190 MW capacity of solar power from its solar PV power plant located in the State of Gujarat seeking indulgence of the Commission to inter alia allow extension of the Scheduled Commercial Operation Date as prescribed under the Power Purchase Agreement on various uncontrollable & justifiable grounds including that of Force Majeure and consequently protecting the Petitioner herein against any financial /commercial prejudice that may ensue under the said PPA.