| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 16/06/2026 11:30 am | 1024/2010 (Remand matter) |
M/s. Tarini Infrastructure Limited
M/s. Tarini Infrastructure Limited
|
GUVNL & Ors.
GUVNL & Ors.
|
Petition for fixation of tariff for two small hydro power projects of 3 MW and 2.6 MW at Daman Ganga Dam/ Madh
Petition for fixation of tariff for two small hydro power projects of 3 MW and 2.6 MW at Daman Ganga Dam/ Madhuban Reservoir under Section 62 read with Section 86(1)(a) of the Electricity Act,2003.
|
__ |
| 2 | 16/06/2026 11:30 am | 2192/2023 |
GWE Infra Projects Pvt. Limited
GWE Infra Projects Pvt. Limited
|
EPD & Ors.
EPD & Ors.
|
Petition under Sections 86 (1) (a) (b) (e) and (f), Section 61 (a) and Section 10 (91) of the Electricity Act,
Petition under Sections 86 (1) (a) (b) (e) and (f), Section 61 (a) and Section 10 (91) of the Electricity Act, 2003 read with Gujarat Government Policy for Small, Scale Distributed Power Projects (SSDSP) notified vide GR No. SLR/11/2019/51/B1 dated 06.03.2019 and approval of for draft PPA and collection of Supervision Charge and Connectivity Charge by the Distribution licensees from the Applicants of SSDSP Projects with respect to GERC Regulations notified vide Notification No. 9 of 2005 and Notification No. 3 of 2011.
|
__ |
| 3 | 16/06/2026 11:30 am | 2494/2025 |
GUVNL & Others
GUVNL & Others
|
|
Petition under Sections 61, 62, 86 (1) (e) of EA, 2003 read with other applicable provisions of the Electricit
Petition under Sections 61, 62, 86 (1) (e) of EA, 2003 read with other applicable provisions of the Electricity Act, 2003 for appropriate order in regard to connectivity sought for during the period from 01.10.2023 to 31.08.2024 by certain class of consumers.
|
__ |
| 4 | 16/06/2026 11:30 am | 2626/2026 |
M/s Epipremnum Aureum Renewables Pvt. Limited & Ors.
M/s Epipremnum Aureum Renewables Pvt. Limited & Ors.
|
GETCO
GETCO
|
Petition is filed under Sections 86 (1) (K) and Section 94 of the Electricity Act, 2003 for seeking clarificat
Petition is filed under Sections 86 (1) (K) and Section 94 of the Electricity Act, 2003 for seeking clarification and Regulatory interpretation and appropriate modi5ication of Clause 5.7(iv) of the Connectivity Procedure, 2025 issued by Gujarat Energy Transmission Corporation Limited (GETCO) and endorsed by the Commission.
|
__ |
| 5 | 16/06/2026 11:30 am | 2634/2026 |
M/s. Saraca Asoca Renewables Pvt. Limited & Ors.
M/s. Saraca Asoca Renewables Pvt. Limited & Ors.
|
GETCO
GETCO
|
Petition is filed under Sections 86 (1) (K) and Section 94 of the Electricity Act, 2003 for seeking clarificat
Petition is filed under Sections 86 (1) (K) and Section 94 of the Electricity Act, 2003 for seeking clarification and Regulatory interpretation and appropriate modification of Clause 5.7(iv) of the Connectivity Procedure, 2025 issued by Gujarat Energy Transmission Corporation Limited (GETCO) and endorsed by the Commission.
|
__ |
| 6 | 16/06/2026 11:30 am | 2660/2026 |
TPL
TPL
|
|
Petition Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 for adoption of tariff discovere
Petition Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 for adoption of tariff discovered under Competitive Bidding Process for Procurement of Firm and Dispatchable Power from Grid connected Renewable Energy Power Projects with Energy Storage Systems through RfS No. TPL/FDRE/01/2025 dated 08.08.2025.
|
__ |