1 26/09/2025 11:30 am 2518/2025
Suzlon Energy Limited
Suzlon Energy Limited
GETCO
GETCO
Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated
Petition under Section 86 (1) (f) of the Electricity Act, 2003 seeking quashing/setting aside the email dated 14.02.2025 and the letter dated 01.03.2025 issued by GETCO thereby illegally rejecting Stage – II connectivity application of the Petitioner qua the infrastructure being developed by it for evacuation of power from its 35 MW Wind Power Project to GETCO’s 66 KV Nadadhri Sub-station for extraneous reasons untenable in the eyes of law.