| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 16/09/2025 11:30 am | 2470/2025 |
M/s Opera Engitech Pvt. Limited
M/s Opera Engitech Pvt. Limited
|
GETCO
GETCO
|
Petition under Section 86 of EA, 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for
Petition under Section 86 of EA, 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial Issues for the State of Gujarat’ passed by the Commission, seeking extension of the Scheduled Date of Commissioning (SCOD) of infrastructure being developed by the Petitioner for evacuation of power from its 6 MW Hybrid Power Plant to the Respondent’s 66KV Gangiyavadar Substation, on account of occurrences and circumstances beyond
the reasonable control of the Petitioner being Force Majeure events.
|
__ |
| 2 | 16/09/2025 11:30 am | 2491/2025 |
TPL
TPL
|
GETCO
GETCO
|
Petition in compliance to the direction (refund of past period STOA charges) issued by the Commission in Order
Petition in compliance to the direction (refund of past period STOA charges) issued by the Commission in Order dated 29.03.2025 in the matter of truing up of FY 2023-24 and determination of ARR & tariff for FY 2025-26 to FY 2029-30 for GETCO.
|
__ |
| 3 | 16/09/2025 11:30 am | 2492/2025 |
TPL
TPL
|
GETCO
GETCO
|
Petition in compliance to the direction (refund of voltage wise Transmission charges and losses) issued by the
Petition in compliance to the direction (refund of voltage wise Transmission charges and losses) issued by the Commission in Order dated 29.03.2025 in the matter of truing up of FY 2023-24 and determination of ARR & tariff for FY 2025-26 to FY 2029-30 for GETCO.
|
__ |
| 4 | 16/09/2025 11:30 am | 2528/2025 |
GUVNL
GUVNL
|
KPI Green Energy Limited
KPI Green Energy Limited
|
Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 for power procurement and
Petition under Section 63 read with Section 86 (1) (b) of the Electricity Act, 2003 for power procurement and adoption of tariff discovered pursuant to the Competitive Bidding Process for procurement of power from Grid connected Wind Power Projects through RfS No. GUVNL/250 MW/
Wind (Phase IX) dated 18.01.2025 & Addendums thereto.
|