Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 03/03/2025 12:30 pm 2314/2024
Project Twelve Renewables Power Pvt. Ltd.
Project Twelve Renewables Power Pvt. Ltd.
GUVNL and GETCO
GUVNL and GETCO
Petition under Section 86 (1) (f) of the Electricity Act, 2003 read with Article 8 of the PPA dated 15.12.2022
Petition under Section 86 (1) (f) of the Electricity Act, 2003 read with Article 8 of the PPA dated 15.12.2022 seeking extension/deferment of the timeline for SCOD on account of Force Majeure events beyond the reasonable control of the Petitioner (i.e. excessive rainfall at the Project site and delay in grant of connectivity for the Project) and consequential reliefs thereto.
__