Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
---|---|---|---|---|---|---|
1 | 19/06/2023 11:30 am | 1788/2019 |
Shri TechTex Pvt. Limited
Shri TechTex Pvt. Limited
|
GETCO & UGVCL
GETCO & UGVCL
|
In the matter under Section 86 (1) (a) and (f) and Section 61 of the Electricity Act, 2003 read with GERC (Lic
In the matter under Section 86 (1) (a) and (f) and Section 61 of the Electricity Act, 2003 read with GERC (Licensee’s Power to recover Expenditure incurred in providing supply and other miscellaneous charges) Regulations, 2005 for recovery of expense from consumer.
|
__ |
2 | 19/06/2023 11:30 am | 1789/2019 |
Shakti Polyweave Pvt. Limited
Shakti Polyweave Pvt. Limited
|
GETCO & UGVCL
GETCO & UGVCL
|
In the matter under Section 86 (1) (a) and (f) and Section 61 of the Electricity Act, 2003 read with GERC (Lic
In the matter under Section 86 (1) (a) and (f) and Section 61 of the Electricity Act, 2003 read with GERC (Licensee’s Power to recover Expenditure incurred in providing supply and other miscellaneous charges) Regulations, 2005 for recovery of expense from consumer.
|
__ |
3 | 19/06/2023 12:30 pm | 2098/2022 & IA No. 02/2023 |
Gujarat Urja Vikas Nigam Limited
Gujarat Urja Vikas Nigam Limited
|
|
In the matter of Petition under Section 86 read with Section 63 of the Electricity Act, 2003 for approval of d
In the matter of Petition under Section 86 read with Section 63 of the Electricity Act, 2003 for approval of deviations from the Guidelines issued by Central Government for procurement of power through Tariff based Competitive Bidding Process from Grid connected Renewable Energy Sources i.e., Wind, Solar and Wind-Solar Hybrid Projects and for approval of bid documents for carrying out bidding process for procurement of power from Hybrid Power Projects having RE generation with co-located Energy Storage Systems.
|
__ |
4 | 19/06/2023 12:30 pm | 2124/2022 |
GIFT Power Company Limited
GIFT Power Company Limited
|
|
In the matter of Petition in accordance with the GERC (Conduct of Business) Regulations, 2004 for seeking appr
In the matter of Petition in accordance with the GERC (Conduct of Business) Regulations, 2004 for seeking approval of PPA to cater the base demand requirement of GIFT City licensee area by executing a PPA with M/s PTC India Limited for supply of power under Medium Term Open Access Booking Basis as per the provisions of ‘Guidelines for Procurement of Power by distribution licensees’ issued by the Commission read with Section 86 (1) (b) of the Electricity Act, 2003.
|
__ |
5 | 19/06/2023 12:30 pm | 2141/2022 |
Gujarat Urja Vikas Nigam Limited
Gujarat Urja Vikas Nigam Limited
|
|
In the matter of Petition under Sections 63, 86 of the Electricity Act, 2003 and Regulation 58 (3) and 80 of G
In the matter of Petition under Sections 63, 86 of the Electricity Act, 2003 and Regulation 58 (3) and 80 of GERC (Conduct of Business) Regulations 2004 for directions and clarification of the Order dated 30.05.2022 passed by the Commission in Petition No. 2068 of 2022 in relation to adoption of tariff discovered under Competitive Bidding Process conducted vide RFS No. GUVNL/500 MW/ Solar (Phase XIII) dated 03.01.2022 issued by GUVNL for Procurement of Power from 500 MW Grid connected Solar Photovoltaic Power Projects in the State of Gujarat.
|
__ |
6 | 19/06/2023 12:30 pm | 2182/2023 |
Shri Jagdamba Polymers Limited
Shri Jagdamba Polymers Limited
|
GETCO & UGVCL
GETCO & UGVCL
|
In the matter of Petition under Section 86 (1) (a) (f) and Section 61 of the Electricity Act, 2003 read with G
In the matter of Petition under Section 86 (1) (a) (f) and Section 61 of the Electricity Act, 2003 read with GERC Regulation No. 9 of 2005, Licensee’s power to recover expenditures incurred in providing supply and other miscellaneous charges and its provisions regarding recovery of expense from consumer and regarding proportionate line charge collected by GETCO.
|
__ |
7 | 19/06/2023 12:30 pm | 2070/2022 & IA No. 14/2022 |
Anisha Power Projects Pvt. Limited
Anisha Power Projects Pvt. Limited
|
GUVNL
GUVNL
|
In the matter of Petition under Section 86 (1) (f) of Electricity Act, 2003 read with Articles 3 (3.3) and 6 (
In the matter of Petition under Section 86 (1) (f) of Electricity Act, 2003 read with Articles 3 (3.3) and 6 (6.6) of the PPA dated 19.08.2019 for adjudication of dispute for non-achievement of Financial Closures and Scheduled Commercial Operation Date due to Force Majeure Event as per Article 8 of the PPA, interalia Act of God.
|
__ |
8 | 19/06/2023 12:30 pm | 2151/2022 |
Jay Chemical Industries Pvt. Limited
Jay Chemical Industries Pvt. Limited
|
MGVCL
MGVCL
|
In the matter of Petition under Section 86 (1) (e) (f) of Electricity Act, 2003 read with Regulations 6.2 &
In the matter of Petition under Section 86 (1) (e) (f) of Electricity Act, 2003 read with Regulations 6.2 & 10.1 of the GERC (Net Metering Solar PV Grid Interactive Systems) Regulations, 2016 for adjudication of disputes in respect to para 11.2 (b) of the Inter Connection Agreement dated 11.09.2017 executed between the parties with regard to captive consumption of 4.3 MW to be allowed to the Petitioner.
|
__ |
9 | 19/06/2023 12:30 pm | 2155/2022 |
Shekhani Industries Pvt. Limited
Shekhani Industries Pvt. Limited
|
UGVCL
UGVCL
|
In the matter of Petition under Section 86 of Electricity Act, 2003 and in the matter of Order dated 11.06.202
In the matter of Petition under Section 86 of Electricity Act, 2003 and in the matter of Order dated 11.06.2021 passed by the Commission in Petition No. 1936/2021 and in the matter of Gujarat Solar Power Policy, 2015 & 2021 and levying of Banking Charges.
|
__ |
10 | 19/06/2023 12:30 pm | 2156/2022 |
Nayara Energy Limited
Nayara Energy Limited
|
SLDC & GETCO
SLDC & GETCO
|
In the matter of Petition under Section 86 of the Electricity Act, 2003 for seeking refund of the amount paid
In the matter of Petition under Section 86 of the Electricity Act, 2003 for seeking refund of the amount paid by the Petitioner as Short-Term Open Access Transmission Charges to the Respondent No. 2 for undertaking purchase of power though Power Exchange for FY 2012-13 and FY 2013-14.
|
__ |
11 | 19/06/2023 12:30 pm | 2192/2023 |
GWE Infra Project Pvt. Limited
GWE Infra Project Pvt. Limited
|
E & P Department, GoG & Others
E & P Department, GoG & Others
|
In the matter of Petition under Sections 86 (1) (a) (b) (e) and (f), Section 61 (a) and Section 10 91) of the
In the matter of Petition under Sections 86 (1) (a) (b) (e) and (f), Section 61 (a) and Section 10 91) of the Electricity Act, 2003 read with Gujarat Government Policy for Small, Scale Distributed Power Projects (SSDSP) notified vide GR No. SLR/11/2019/51/B1 dated 06.03.2019 and approval of for draft PPA and collection of Supervision Charge and Connectivity Charge by the Distribution licensees from the Applicants of SSDSP Projects with respect to GERC Regulations notified vide Notification No. 9 of 2005 and Notification No. 3 of 2011.
|