Hearing Schedule
Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
---|---|---|---|---|---|---|
1 | 15/05/2023 11:30 am | 2138/2022 & IA No. 09/2023 |
Integrated Coal Mining Limited
Integrated Coal Mining Limited
|
GUVNL
GUVNL
|
In the matter of Petition under Section 86(1) (e) & (f) of the Electricity Act, 2003 read with Clause 10 o
In the matter of Petition under Section 86(1) (e) & (f) of the Electricity Act, 2003 read with Clause 10 of the PPA dated 07.12.2010 for adjudication of dispute between the Petitioner and the Respondent regarding replacement of damaged and defective Solar PV modules, quashing of letter dated 03.09.2020 issued by the Respondent and direction to Respondent for allowing replacement of all damaged and defective solar modules.
|
__ |