Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 10/10/2022 11:30 am 1738/2018
Rudra Global Infra Products Limited
Rudra Global Infra Products Limited
PGVCL & Others
PGVCL & Others
Petition under Section 86 (1) (e) and (f), Section 61 and Section 94 of the Electricity Act, 2003 read with Re
Petition under Section 86 (1) (e) and (f), Section 61 and Section 94 of the Electricity Act, 2003 read with Regulations 23 and 80 of the GERC (Conduct of Business) Regulations, 2004 read with Order No. 2 of 2016 and its provisions regarding banking of energy generated by WEG in Gujarat State.
__
2 10/10/2022 11:30 am 1739/2018
Sims Ceramics Pvt. Limited
Sims Ceramics Pvt. Limited
PGVCL & Others
PGVCL & Others
Petition under Section 86 (1) (e) and (f), Section 61 and Section 94 of the Electricity Act, 2003 read with Re
Petition under Section 86 (1) (e) and (f), Section 61 and Section 94 of the Electricity Act, 2003 read with Regulations 23 and 80 of the GERC (Conduct of Business) Regulations, 2004 read with Order No. 2 of 2016 and its provisions regarding banking of energy generated by WEG in Gujarat State.
__
3 10/10/2022 11:30 am 1749/2018
Madhu Silica Private Limited
Madhu Silica Private Limited
PGVCL & Others
PGVCL & Others
Petition under Section 86 (1) (e) and (f), Section 61 and Section 94 of the Electricity Act, 2003 read with Re
Petition under Section 86 (1) (e) and (f), Section 61 and Section 94 of the Electricity Act, 2003 read with Regulations 23 and 80 of the GERC (Conduct of Business) Regulations, 2004 read with Order No. 2 of 2016 and its provisions regarding banking of energy generated by WEG in Gujarat State.
__
4 10/10/2022 12:00 pm 1891/2020
INEOS Styrolution India Ltd.
INEOS Styrolution India Ltd.
MGVCL & Others
MGVCL & Others
Petition under Section 86 (1) (f) for non-grant of Set Off in respect of power generated from the various Wind
Petition under Section 86 (1) (f) for non-grant of Set Off in respect of power generated from the various Wind Farms of the Petition and wrongful recovery of amount of set off and transmission.
__
5 10/10/2022 12:00 pm 2017/2021
Bhavani Industries
Bhavani Industries
UGVCL & GETCO
UGVCL & GETCO
Petition under Section 86 (1) (b), (e), (f) of the Electricity Act, 2003, for dispute regarding levying of tra
Petition under Section 86 (1) (b), (e), (f) of the Electricity Act, 2003, for dispute regarding levying of transmission charges, wheeling charges, not providing banking and purchase of surplus energy in terms of Wheeling Agreement dated 25.02.2015 with GETCO and Wheeling Agreement dated 27.02.2015 with UGVCL.
__
6 10/10/2022 12:00 pm 2092/2022
Virgo Aluminium Limited
Virgo Aluminium Limited
MGVCL & GETCO
MGVCL & GETCO
Petition dated 27.04.2022, in the matter of Petition under Sections 42, 43, 50, 86 and other applicable provis
Petition dated 27.04.2022, in the matter of Petition under Sections 42, 43, 50, 86 and other applicable provisions of the Electricity Act, 2003 read with GERC (Electricity Supply Code and Related Matters) Regulations, 2015, GERC (Standard of Performance of Distribution Licensee) Regulations, 2005 and other applicable Regulations of the GERC for seeking deemed extension of time for completion of 66 kV transmission line for 5000 kVA contract demand on post-facto basis and consequently directing MGVCL to consider 60 days’ notice period from the deemed extended date and to refund minimum demand charges levied by MGVCL on deemed release basis on 5000 kVA contract demand till physical release of connection.
__
7 10/10/2022 12:00 pm 2146/2022
GUVNL
GUVNL
In the matter of the petition for approval of short-term arrangement of power pursuant to selection of succes
In the matter of the petition for approval of short-term arrangement of power pursuant to selection of successful bidders through DEEP portal of Ministry of Power, Government of India, for the period from 01.09.2022 to 31.12.2022 and the Commission’s guidelines dated 14.08.2013.
__
8 10/10/2022 12:00 pm 2150/2022
GUVNL
GUVNL
In the matter of the petition for approval of short-term arrangement of power pursuant to selection of succes
In the matter of the petition for approval of short-term arrangement of power pursuant to selection of successful bidders through DEEP portal of Ministry of Power, Government of India, for the period from 03.10.2022 to 21.10.2022 and the Commission’s guidelines dated 14.08.2013.
__