1 30/08/2022 11:30 am 2070/2022 & IA No. 14/2022
Anisha Power Projects Pvt. Limited
Anisha Power Projects Pvt. Limited
GUVNL
GUVNL
In the matter of Petition under Section 86 (1) (f) of Electricity Act, 2003 read with Articles 3 (3.3) and 6 (
In the matter of Petition under Section 86 (1) (f) of Electricity Act, 2003 read with Articles 3 (3.3) and 6 (6.6) of the PPA dated 19.08.2019 for adjudication of dispute for non-achievement of Financial Closures and Scheduled Commercial Operation Date due to Force Majeure Event as per Article 8 of the PPA, interalia Act of God.