Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 15/10/2019 11:30 am 1805/2019
TPL-D (Ahd. & Gandhinagar)
TPL-D (Ahd. & Gandhinagar)
Petition for Clarification/Rectification Petition against GERC Order No. 1764/2018 dated 24.04.2019 for Truing
Petition for Clarification/Rectification Petition against GERC Order No. 1764/2018 dated 24.04.2019 for Truing-up of FY 2017-18 and Determination of Tariff for FY 2019-20 for TPL’s Distribution Business of Ahmedabad Supply Area.
__
2 15/10/2019 11:30 am 1806/2019
TPL-D (Surat)
TPL-D (Surat)
Petition for Clarification/Rectification Petition against GERC Order No. 1765/2018 dated 24.04.2019 for Truing
Petition for Clarification/Rectification Petition against GERC Order No. 1765/2018 dated 24.04.2019 for Truing-up of FY 2017-18 and Determination of Tariff for FY 2019-20 for TPL’s Distribution Business of Surat Supply Area.
__
3 15/10/2019 11:30 am 1809/2019
TPL-D
TPL-D
Petition for Clarification/Rectification Petition against GERC Order No. 1757/2018 dated 24.04.2019 for Truing
Petition for Clarification/Rectification Petition against GERC Order No. 1757/2018 dated 24.04.2019 for Truing-up of FY 2017-18 and Determination of Tariff for FY 2019-20 for Gujarat Energy Transmission Corporation Limited (GETCO).
__
4 15/10/2019 11:30 am 1808/2019
GUVNL & Others
GUVNL & Others
In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Second Amendment) Re
In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Second Amendment) Regulations 2018 for revision in renewable Power Purchase Obligation (RPO) in case of four subsidiary distribution Company of GUVNL for FY 2018-19
__
5 15/10/2019 11:30 am Review Petition No. 1704/2018
Laghu Udyog Bharti, Gujarat & Other
Laghu Udyog Bharti, Gujarat & Other
Energy & Petrochemicals Department, GoG & Others
Energy & Petrochemicals Department, GoG & Others
In the matter of Review Petition under Section 94 of Electricity Act, 2003 read with Order 47, Rule 1 of Code
In the matter of Review Petition under Section 94 of Electricity Act, 2003 read with Order 47, Rule 1 of Code of Civil Procedure Code, 1908 and Regulation 72 of GERC (Conduct of Business) Regulations, 2004 for review the Commission’s order dated 23.10.2017 in Petition No. 1654 of 2017 – to decide the extension of applicability of Generic Tariff Order No. 04 of 2016 dated 10.11.2016.
__
6 15/10/2019 11:30 am 1808/2019
GUVNL & Others
GUVNL & Others

In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Se

In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Second

Amendment) Regulations 2018 for revision in renewable Power Purchase Obligation (RPO) in case of four

subsidiary distribution Company of GUVNL for FY 2018-19

__