Hearing Schedule
Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
---|---|---|---|---|---|---|
1 | 15/10/2019 11:30 am | 1805/2019 |
TPL-D (Ahd. & Gandhinagar)
TPL-D (Ahd. & Gandhinagar)
|
|
Petition for Clarification/Rectification Petition against GERC Order No. 1764/2018 dated 24.04.2019 for Truing
Petition for Clarification/Rectification Petition against GERC Order No. 1764/2018 dated 24.04.2019 for Truing-up of FY 2017-18 and Determination of Tariff for FY 2019-20 for TPL’s Distribution Business of Ahmedabad Supply Area.
|
__ |
2 | 15/10/2019 11:30 am | 1806/2019 |
TPL-D (Surat)
TPL-D (Surat)
|
|
Petition for Clarification/Rectification Petition against GERC Order No. 1765/2018 dated 24.04.2019 for Truing
Petition for Clarification/Rectification Petition against GERC Order No. 1765/2018 dated 24.04.2019 for Truing-up of FY 2017-18 and Determination of Tariff for FY 2019-20 for TPL’s Distribution Business of Surat Supply Area.
|
__ |
3 | 15/10/2019 11:30 am | 1809/2019 |
TPL-D
TPL-D
|
|
Petition for Clarification/Rectification Petition against GERC Order No. 1757/2018 dated 24.04.2019 for Truing
Petition for Clarification/Rectification Petition against GERC Order No. 1757/2018 dated 24.04.2019 for Truing-up of FY 2017-18 and Determination of Tariff for FY 2019-20 for Gujarat Energy Transmission Corporation Limited (GETCO).
|
__ |
4 | 15/10/2019 11:30 am | 1808/2019 |
GUVNL & Others
GUVNL & Others
|
|
In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Second Amendment) Re
In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Second Amendment) Regulations 2018 for revision in renewable Power Purchase Obligation (RPO) in case of four subsidiary distribution Company of GUVNL for FY 2018-19
|
__ |
5 | 15/10/2019 11:30 am | Review Petition No. 1704/2018 |
Laghu Udyog Bharti, Gujarat & Other
Laghu Udyog Bharti, Gujarat & Other
|
Energy & Petrochemicals Department, GoG & Others
Energy & Petrochemicals Department, GoG & Others
|
In the matter of Review Petition under Section 94 of Electricity Act, 2003 read with Order 47, Rule 1 of Code
In the matter of Review Petition under Section 94 of Electricity Act, 2003 read with Order 47, Rule 1 of Code of
Civil Procedure Code, 1908 and Regulation 72 of GERC (Conduct of Business) Regulations, 2004 for review the
Commission’s order dated 23.10.2017 in Petition No. 1654 of 2017 – to decide the extension of applicability of
Generic Tariff Order No. 04 of 2016 dated 10.11.2016.
|
__ |
6 | 15/10/2019 11:30 am | 1808/2019 |
GUVNL & Others
GUVNL & Others
|
|
In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Se In the matter of GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 & (Second Amendment) Regulations 2018 for revision in renewable Power Purchase Obligation (RPO) in case of four subsidiary distribution Company of GUVNL for FY 2018-19 |
__ |