Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 18/08/2018 11:30 am 1364/2013 (Remand Matter)
M/s. Taxus Infrastructure & Power Projects Private Limited
M/s. Taxus Infrastructure & Power Projects Private Limited
GEDA, GUVNL, GETCO, CEI and SLDC
GEDA, GUVNL, GETCO, CEI and SLDC
In the matter of filing of petition under section 86(1) (f) of the Electricity Act, 2003 for declaring (i) 5 M
In the matter of filing of petition under section 86(1) (f) of the Electricity Act, 2003 for declaring (i) 5 MW Solar Photo Voltaic (PV) power project set-up by the Petitioner commissioned on 31st March, 2013 instead of 8th August, 2013, (ii) Petitioner is entitled to receive tariff at the rate of Rs. 11.25/kWh instead of Rs. 10.40/kWh paid by the Respondent No. 2 GUVNL and direct the Respondent to pay an amount of Rs. 2,69,86,837 for supply of electricity by the Petitioner from 31st March 2013