Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 03/04/2018 11:30 am LA No. 2 of 2018
MPSEZ Utilities Private Limited
MPSEZ Utilities Private Limited
In the matter of filing the application for grant of distribution license in the area of Dholera Special Inves
In the matter of filing the application for grant of distribution license in the area of Dholera Special Investment Region (SIR), District – Ahmedabad, Gujarat.
__
2 03/04/2018 11:30 am Review Petition No. 1704/2018
LUB – Gujarat and UUWA
LUB – Gujarat and UUWA
In the matter of filing review petition under Section 94 of the Electricity Act, 2003 read with Order 47, Rule
In the matter of filing review petition under Section 94 of the Electricity Act, 2003 read with Order 47, Rule 1 of Code of Civil Procedure, 1908 and Regulation 72 of GERC (Conduct of Business) Regulations, 2004, for review the Commission’s order dated 23.10.2017 in Petition No. 1654 of 2017 – to decide the extension of applicability of Generic Tariff Order No. 04 of 2016 dated 10.11.2016.
__
3 03/04/2018 11:30 am 1244/2012 And IA No. 03/2014, IA No. 07/2016 and I
M/s. Bhavnagar Biomass Projects Pvt. Limited
M/s. Bhavnagar Biomass Projects Pvt. Limited
GUVNL and GEDA
GUVNL and GEDA
Petition under section 86 (1) (f) of the EA 2003 for directions to the respondents to pay the amounts due to t
Petition under section 86 (1) (f) of the EA 2003 for directions to the respondents to pay the amounts due to the petitioner in terms of the invoices raised and for re-determination of fuel cost fixation of tariff of the biomass based 10 MW power plant at Bhavnagar u/s. 62 r/w. sec. 81(1) (e) of the EA, 2003.
__
4 03/04/2018 11:30 am 1114/2011 And IA No. 04/2014, IA No. 06/2016, IA N
Junagadh Power Projects Pvt. Limited
Junagadh Power Projects Pvt. Limited
GUVNL, GETCO, GEDA, SLDC
GUVNL, GETCO, GEDA, SLDC
Re-determination of fuel cost, fixation of tariff and non-applicability of Intra-State Availability based tari
Re-determination of fuel cost, fixation of tariff and non-applicability of Intra-State Availability based tariff to the biomass based 10MW power plant at Amreli under section 62 read with section 81(1) (a) of the Electricity Act, 2003.
__
5 03/04/2018 11:30 am 1113/2011 And IA No. 05/2014, IA No. 05 /2016, IA
Amreli Power Projects Pvt. Limited
Amreli Power Projects Pvt. Limited
GUVNL, GETCO, GEDA, SLDC
GUVNL, GETCO, GEDA, SLDC
In the matter of re-determination of fuel cost and fixation of tariff and non-applicability of intra-state ava
In the matter of re-determination of fuel cost and fixation of tariff and non-applicability of intra-state availability based tariff to the biomass based 10MW power plant at Amreli and Junagadh under section 62 read with section 86(1) (a) of the Electricity Act, 2003.
__
6 03/04/2018 11:30 am 1024/2010 And IA No.08/2016
M/s. Tarini Infrastructure Ltd.
M/s. Tarini Infrastructure Ltd.
GUVNL, Narmada Water Resources and GETCO
GUVNL, Narmada Water Resources and GETCO
Petition for fixation of tariff for two small hydro power projects of 3 MW and 2.6 MW at Daman Ganga Dam/ Madh
Petition for fixation of tariff for two small hydro power projects of 3 MW and 2.6 MW at Daman Ganga Dam/ Madhuban Reservoir under Section 62 read with Section 86 (1) (a) of the EA, 2003.
__
7 03/04/2018 11:30 am 1437/2014
Torrent Power Limited
Torrent Power Limited
Petition for minimum quantum of purchase (%) from Renewable energy sources % targets for the year FY 2013-14 i
Petition for minimum quantum of purchase (%) from Renewable energy sources % targets for the year FY 2013-14 in view of the supply constraints or other factors beyond the control of the licensee under the provisions of the Reg. 4.2 of GERC (procurement of energy from Renewables Sources) regulation, 2010.
__
8 03/04/2018 11:30 am 1711/2018
Torrent Power Limited
Torrent Power Limited
In the matter of Petition for approval of Short Term Power Purchase arrangement for sourcing of power to cater
In the matter of Petition for approval of Short Term Power Purchase arrangement for sourcing of power to cater to the demand of Dahej SEZ License Area under the provisions of the Guidelines for Power Procurement by Distribution Licensee issued by the Commission read with Section 86 (1) (b) of the Electricity Act, 2003.
__