1 20/01/2018 11:30 am 1680 of 2017 & IA No. 16 of 2017
Essar Power Gujarat Limited
Essar Power Gujarat Limited
Gujarat Urja Vikas Nigam Limited
Gujarat Urja Vikas Nigam Limited
In the matter of petition under Section 86 (1) (f) of the Electricity Act, 2003 read with Article 17 of PPA da
In the matter of petition under Section 86 (1) (f) of the Electricity Act, 2003 read with Article 17 of PPA dated 26.02.2007 executed between EPGL and GUVNL with respect to 1200 MW Salaya – I Thermal Power Project implemented by Essar Power Gujarat Limited.
__
2 20/01/2018 11:30 am 972/2009
GUVNL
GUVNL
Essar Power Limited
Essar Power Limited
In the matter of petition for adjudication of the dispute that have arisen between the petitioner and the resp