Hearing Schedule
| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 29/12/2017 11:30 am | 1658/2017 |
Giriraj Enterprises & Others
Giriraj Enterprises & Others
|
GUVNL & Others
GUVNL & Others
|
In the matter of Petition under Sections 86 (1) (a) (b) (e) (f) (k) read with Section 62 of the Electricity Ac
In the matter of Petition under Sections 86 (1) (a) (b) (e) (f) (k) read with Section 62 of the Electricity Act, 2003 seeking direction against the Respondent No. 1 to execute Power Purchase Agreements with Wind Power Producers within the State in terms of the Order No. 02 of 2016 dated 30.08.2016 passed by the Commission.
|
__ |
| 2 | 29/12/2017 11:30 am | 1659/2017 |
IWPA and OIL
IWPA and OIL
|
GUVNL & Others
GUVNL & Others
|
In the matter of Petition under Sections 86 (1) (a) (b) (e) (f) (k) read with Section 62 of the Electricity Ac
In the matter of Petition under Sections 86 (1) (a) (b) (e) (f) (k) read with Section 62 of the Electricity Act, 2003 seeking direction against the Respondent No. 1 to execute Power Purchase Agreements with Wind Power Producers within the State in terms of the Order No. 02 of 2016 dated 30.08.2016 passed by the Commission.
|
__ |
| 3 | 29/12/2017 11:30 am | 1667/2017 |
Jai Bharat Gum Limited & Chemicals Limited & Others
Jai Bharat Gum Limited & Chemicals Limited & Others
|
GUVNL & Others
GUVNL & Others
|
In the matter of Petition under Sections 86 (1) (a) (b) (e) (f) (k) read with Section 62 of the Electricity Ac
In the matter of Petition under Sections 86 (1) (a) (b) (e) (f) (k) read with Section 62 of the Electricity Act, 2003 seeking direction against the Respondent No. 1 to execute Power Purchase Agreements with Wind Power Producers within the State in terms of the Order No. 02 of 2016 dated 30.08.2016 passed by the Commission.
|
__ |
| 4 | 29/12/2017 11:30 am | 1676 of 2017 & IA No. 17 of 2017 |
GUVNL
GUVNL
|
Adani Green Energy Limited & Others
Adani Green Energy Limited & Others
|
In the matter under Section 86 (1) (b) and other applicable provisions of the Electricity Act, 2003 for seekin
In the matter under Section 86 (1) (b) and other applicable provisions of the Electricity Act, 2003 for seeking approval of PPAs executed by GUVNL with Wind Power Projects at the Tariff of Rs. 3.46 per unit in accordance with the approval of Government of Gujarat and pursuant to request of various projects developers for considering the tariff of Rs. 3.46 per unit discovered under competitive bidding process initiated by SECI under MNRE Guidelines as benchmark tariff.
|
__ |
| 5 | 29/12/2017 11:30 am | 1678/2017 |
Surya Vidyut Limited
Surya Vidyut Limited
|
GUVNL
GUVNL
|
In the matter of petition under Section 86 of the Electricity Act, 2003 for approval of the Power Purchase Agr
In the matter of petition under Section 86 of the Electricity Act, 2003 for approval of the Power Purchase Agreement dated 31.03.2017 for supply of 10 MW executed with Gujarat Urja Vikas Nigam Limited.
|
__ |
| 6 | 29/12/2017 11:30 am | 1679/2017 |
Surya Vidyut Limited
Surya Vidyut Limited
|
GUVNL
GUVNL
|
In the matter of petition under Section 86 of the Electricity Act, 2003 for approval of the Power Purchase Agr
In the matter of petition under Section 86 of the Electricity Act, 2003 for approval of the Power Purchase Agreement dated 31.03.2017 for supply of 2 MW executed with Gujarat Urja Vikas Nigam Limited.
|
__ |
| 7 | 29/12/2017 11:30 am | 1681/2017 |
Powerica Limited
Powerica Limited
|
GUVNL
GUVNL
|
In the matter of petition under Sections 3(1), 61 (h), 62 (1)(a) and 86 (1) (e) of the Electricity Act, 2003 a
In the matter of petition under Sections 3(1), 61 (h), 62 (1)(a) and 86 (1) (e) of the Electricity Act, 2003 alongwith guidelines and directions issued by the GERC from time to time and under Part VII of the Electricity Act, 2003 read with relevant guidelines and Regulations, for the appropriate order for PPA and tariff determination.
|
__ |