| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 04/07/2017 11:30 am | 1511/2015 |
Shapoorji Pallonji Energy (Gujarat) Private Limited
Shapoorji Pallonji Energy (Gujarat) Private Limited
|
Gujarat Urja Vikas Nigam Limited
Gujarat Urja Vikas Nigam Limited
|
In the matter of adjudication of disputes under Sections 61,63 and 86 of the Electricity Act, 2003 read with R
In the matter of adjudication of disputes under Sections 61,63 and 86 of the Electricity Act, 2003 read with Regulations 23 and 80 of GERC (Conduct of Business) Regulations and PPA dated 15.05.2010 executed between the parties.
|
__ |
| 2 | 04/07/2017 11:30 am | 1477/2015 |
OPGS Power Gujarat Private Limited
OPGS Power Gujarat Private Limited
|
GETCO
GETCO
|
In the matter of petition under section 86 (1) (c) and (f) of the Electricity Act, 2003 read with Regulation 4
In the matter of petition under section 86 (1) (c) and (f) of the Electricity Act, 2003 read with Regulation 45 of the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 and Regulations 80 and 82 of the GERC (Conduct of Business) Regulations, 2004 and extension of the effective date of payment of transmission charges under Bulk Power Transmission Agreement dated 21.12.2010 executed between the OPGS Power Gujarat Private Limited and Gujarat Energy Transmission Corporation Li
|
__ |
| 3 | 04/07/2017 11:30 am | 1526/2015 |
GUVNL
GUVNL
|
Shapoorji Pallonji Energy (Gujarat) Private Limited
Shapoorji Pallonji Energy (Gujarat) Private Limited
|
In the matter under Section 86 (1) (f) of the Electricity Act, 2003 in regard to dispute arising out of the PP
In the matter under Section 86 (1) (f) of the Electricity Act, 2003 in regard to dispute arising out of the PPA dated 15.05.2010 between GUVNL and M/s. Shapoorji Pallonji Energy (Gujarat) Pvt. Limited
|
__ |
| 4 | 04/07/2017 11:30 am | 1527/2015 |
GUVNL
GUVNL
|
Essar Power Gujarat Limited
Essar Power Gujarat Limited
|
In the matter under Section 86 (1) (f) of the Electricity Act, 2003 in regard to dispute arising out of the PP
In the matter under Section 86 (1) (f) of the Electricity Act, 2003 in regard to dispute arising out of the PPA dated 15.05.2010 between GUVNL and M/s. Essar Power Gujarat Limited.
|
__ |
| 5 | 04/07/2017 11:30 am | 1532/2015 |
Essar Power Gujarat Limited
Essar Power Gujarat Limited
|
GUVNL
GUVNL
|
In the matter of adjudication of dispute under section 86 (1) (f) of the Electricity Act, 2003 read with Artic
In the matter of adjudication of dispute under section 86 (1) (f) of the Electricity Act, 2003 read with Article 14 of the PPA dated 15.05.2010 executed between Essar Power Gujarat Limited and Gujarat Urja Vikas Nigam Limited.
|
__ |
| 6 | 04/07/2017 11:30 am | 1606/2016 |
OPGS Power Gujarat Private Limited
OPGS Power Gujarat Private Limited
|
GETCO
GETCO
|
In the matter of petition under section 86 (1) (c) read with Section 86 (1) (f) of the Electricity Act, 2003 f
In the matter of petition under section 86 (1) (c) read with Section 86 (1) (f) of the Electricity Act, 2003 for adjudication of disputes between the parties.
|
__ |
| 7 | 04/07/2017 11:30 am | 1614/2016 |
Shah Alloys Limited
Shah Alloys Limited
|
SLDC
SLDC
|
In the matter under the provisions of GERC (Terms and Conditions for Open Access) Regulations, 2011 for denial
In the matter under the provisions of GERC (Terms and Conditions for Open Access) Regulations, 2011 for denial of Short Term Open Access permission.
|