| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 10/03/2015 11:30 am | ReviewPetition No.1476/2015 |
Abellon Clean Ahmedabad Limited
Abellon Clean Ahmedabad Limited
|
GUVNL & Others
GUVNL & Others
|
In the matter under section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 72 of the GERC (Condu
In the matter under section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 72 of the GERC (Conduct of Business) Regulations, 2004 seeking review of the order of the Commission dated 23.12.2014 in Petition No. 1334 of 2013.
|
__ |
| 2 | 10/03/2015 11:30 am | 1478/2015 |
M/s. Shantigram Estate Management Private Limited
M/s. Shantigram Estate Management Private Limited
|
UGVCL
UGVCL
|
In the matter of petition under section 61, 62, 64, 86 and other applicable provisions of the Electricity Act,
In the matter of petition under section 61, 62, 64, 86 and other applicable provisions of the Electricity Act, 2003 for Petitioner’s Electric Connection No. HT-18088 for construction purpose and in the matter of the applicable tariff rate HTP – I instead of tariff rate HTP –III as per the relevant tariff order and the regulations
|
__ |
| 3 | 10/03/2015 11:30 am | 1480/2015 |
SLDC
SLDC
|
GUVNL & Others
GUVNL & Others
|
In the matter of devising a mechanism for recovery of compensatory charges from entity (ies) who are in deviat
In the matter of devising a mechanism for recovery of compensatory charges from entity (ies) who are in deviation to schedule and for whom a generating station of any entity is scheduled by State Load Dispatch Centre to ensure over drawl/under drawl at regional periphery as stipulated by Central Commission.
|
__ |
| 4 | 10/03/2015 11:30 am | 1481/2015 |
Torrent Power Limited Torrent Energy Limited
Torrent Power Limited Torrent Energy Limited
|
GUVNL
GUVNL
|
In the matter of approval of short term power purchase arrangement for sourcing of power from M/s GUVNL to cat
In the matter of approval of short term power purchase arrangement for sourcing of power from M/s GUVNL to cater to the demand of Ahmedabad, Gandhinagar, Surat and Dahej SEZ license areas under the provisions of the Guidelines for Power Procurement by Distribution licensee issued by the Hon’ble Commission read with Section 86 (1) (b) of the Electricity Act 2003.
|
__ |
| 5 | 10/03/2015 11:30 am | 1482/2014 |
Sand Land Real Estates Pvt. Limited
Sand Land Real Estates Pvt. Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |
| 6 | 10/03/2015 11:30 am | 1483/2014 |
Responsive SUTIP Limited
Responsive SUTIP Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |
| 7 | 10/03/2015 11:30 am | 1484/2014 |
Hiraco Renewable Energy Private Limited
Hiraco Renewable Energy Private Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |
| 8 | 10/03/2015 11:30 am | 1485/2014 |
CBC Solar Technologies Private Limited
CBC Solar Technologies Private Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |
| 9 | 10/03/2015 11:30 am | 1486/2014 |
Chattel Constructions Private Limited
Chattel Constructions Private Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |
| 10 | 10/03/2015 11:30 am | 1487/2014 |
Ganeshvani Merchandise Private Limited
Ganeshvani Merchandise Private Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |
| 11 | 10/03/2015 11:30 am | 1488/2015 |
Ganges Green Energy Private Limited
Ganges Green Energy Private Limited
|
GUVNL
GUVNL
|
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read
In the matter of petition under regulations 62 and 64 of the GERC (Conduct of Business) Regulations, 2004 read with sections 86 (1) (f) and 142 of the Electricity Act, 2003 for enforcement of Order No.1 of 2012 dated 27.01.2014 and Order dated 08.08.2013 passed by the Commission in Petition No. 1270 of 2012 in the matter of adjudication of disputes under the PPA dated 09.12.2010 and supplementary PPA dated 07.05.2011 between EMCO Limited and GUVNL.
|
__ |