Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 20/12/2014 11:30 am 1433/2014
CLP Power India Private Limited
CLP Power India Private Limited
GUVNL
GUVNL
In the matter of filing of petition under section 86 (1) (f) of the Electricity Act, 2003 in relation to the P
In the matter of filing of petition under section 86 (1) (f) of the Electricity Act, 2003 in relation to the Power Purchase Agreement dated 03.02.1994 between the parties.
__
2 20/12/2014 11:30 am 1449/2014
Gujarat Granito Manufacturer’s Association
Gujarat Granito Manufacturer’s Association
PGVCL
PGVCL
In the matter of filing petition under section 94 of the Electricity Act, 2003 read with Regulation 26.1 of GE
In the matter of filing petition under section 94 of the Electricity Act, 2003 read with Regulation 26.1 of GERC Regulation 2 of 2004, read with Regulations 32.3 and 45 of GERC Regulation 3 of 2011 for not providing compensation for underdrawal by distribution licensee PGVCL as a result of non- availability of distribution system or unscheduled shut down.
__
3 20/12/2014 11:30 am 1454/2014
PGVCL, DGVCL, UGVCL, and MGVCL
PGVCL, DGVCL, UGVCL, and MGVCL
In the matter of filing petition under section 86 of the Electricity Act, 2003 for directions in the matter of
In the matter of filing petition under section 86 of the Electricity Act, 2003 for directions in the matter of guidelines dated 04.06.2014 issued by the office of the Commission
__
4 20/12/2014 11:30 am 1333/2013
M/s. Cargo Solar Power Gujarat Private Limited
M/s. Cargo Solar Power Gujarat Private Limited
GUVNL
GUVNL
In the matter of seeking adjudication of dispute under section 86 (1)(f) of the Electricity Act, 2003 in terms
In the matter of seeking adjudication of dispute under section 86 (1)(f) of the Electricity Act, 2003 in terms of the Power Purchase Agreement dated 30.04.2010 for 25 MW Solar Power Project of M/s Cargo Solar Power Gujarat Pvt. Limited with GUVNL regarding (i) considering the period from 07.04.2012 to 31.07.2013 as Force Majeure Event; and (ii) changes in the definition of Construction Default Date, Schedule Commercial Operation Date (SCOD), Article 2.2 pertaining to Licences, permits and conditions precedents, Article 4.3 pertaining to liquidated damages for delay in commissioning the project/solar thermal grid interconnectivity power plant beyond Schedule Commercial Operation Date and extend the time limit for Schedule Commercial Operation Date from 31.07.2013 to 31.12.2014.
__
5 20/12/2014 11:30 am 1337/2013
Solar Semiconductor Power Company (India) Private Limited
Solar Semiconductor Power Company (India) Private Limited
GUVNL
GUVNL
In the matter of adjudication of disputes under Power Purchase Agreement dated 30.04.2010 and Supplementary Po
In the matter of adjudication of disputes under Power Purchase Agreement dated 30.04.2010 and Supplementary Power Purchase Agreements dated 27.10.2010 and 10.05.2011 between Solar Semiconductor Power Company (India) Private Limited and Gujarat Urja Vikas Nigam Limited under section 86 (1) (f) of the Electricity Act, 2003.
__
6 20/12/2014 11:30 am 1401/2014
Essar Steel India Limited
Essar Steel India Limited
GECTO and DGVCL
GECTO and DGVCL
n the matter of filing petition under section 86 (1) (f) of the Electricity Act, 2003 for refund of Parallel O
n the matter of filing petition under section 86 (1) (f) of the Electricity Act, 2003 for refund of Parallel Operation Charges.
__
7 20/12/2014 11:30 am 1420/2014 and I.A. No. 07/2014.
Essar Steel India Limited
Essar Steel India Limited
GUVNL and DGVCL
GUVNL and DGVCL
In the matter of filing petition under section 86 (1) (f) of the Electricity Act, 2003, seeking adjudication o
In the matter of filing petition under section 86 (1) (f) of the Electricity Act, 2003, seeking adjudication of the dispute between the parties with respect to levy of cross subsidy surcharge in terms of section 42 (2) of the Electricity Act, 2003 read with Rule 3 of the Electricity Rules, 2005
__
8 20/12/2014 11:30 am 1424/2014
Oreva Energy Private Limited
Oreva Energy Private Limited
GUVNL
GUVNL
In the matter of petition of adjudication of dispute under section 86(1) (f) of the Electricity Act, 2003 read
In the matter of petition of adjudication of dispute under section 86(1) (f) of the Electricity Act, 2003 read with Article 8 of the Power Purchase Agreement dated 07.08.2008 executed between the petitioner and GUVNL, regarding wrongful levy of liquidated damage/ penalty amount of Rs. 44 Lakhs due to non- availability of the targeted generation during the FY 2012-2013 was a Force Majeure event as per the provisions of the PPA.
__
9 20/12/2014 11:30 am 1404/2014
Essar Power Gujarat Limited Essar Power Limited
Essar Power Gujarat Limited Essar Power Limited
GUVNL
GUVNL
In the matter under section 86 (1) (f) read with 86 (1) (b) of the Electricity Act, 2003 for dispute between a
In the matter under section 86 (1) (f) read with 86 (1) (b) of the Electricity Act, 2003 for dispute between a generating company and the distribution licensee on account of the wrongful deductions carried out by the distribution licensee for the power supplied during the FY 2012-2013.
__
10 20/12/2014 11:30 am 1365/2013
M/s. TADAS Wind Energy Private Limited
M/s. TADAS Wind Energy Private Limited
GUVNL
GUVNL
In the matter of filing of petition for determination and/or redetermination of Tariff for procurement of powe
In the matter of filing of petition for determination and/or redetermination of Tariff for procurement of power by distribution licensees from wind energy generators and other commercial issues.
__
11 20/12/2014 11:30 am 1429/2014
Essar Oil Limited
Essar Oil Limited
GETCO and PGVCL
GETCO and PGVCL
In the matter of petition under section 86 (1) (f) of the Electricity Act, 2003 for unlawful recovery of Paral
In the matter of petition under section 86 (1) (f) of the Electricity Act, 2003 for unlawful recovery of Parallel Operation Charges by PGVCL qua Essar Oil Limited’s Captive Power Plant operating in parallel with GETCO’s grid for the period from 13.09.2006 till 01.06.2011.
__