Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 30/08/2014 11:30 am 1387/2013
M/s. Welspun Corp. Limited
M/s. Welspun Corp. Limited
PGVCL, GETCO & SLDC
PGVCL, GETCO & SLDC
Petition for illegal recovery of power factor penalty by distribution licensee and consequent refund thereof.
Petition for illegal recovery of power factor penalty by distribution licensee and consequent refund thereof.
__
2 30/08/2014 11:30 am Petition No.1389/2014 And I. A. No. 01/2014
Essar Power Gujarat Limited Essar Power Limited
Essar Power Gujarat Limited Essar Power Limited
GUVNL, CERS, UUWA, Laghu Udhyog Bharti, Shri Pravinbhai Hamirbhai Madam, Shri Amarsinh Chavda, Shri Kanubhai Patel, Shri Bipinbhai Patel
GUVNL, CERS, UUWA, Laghu Udhyog Bharti, Shri Pravinbhai Hamirbhai Madam, Shri Amarsinh Chavda, Shri Kanubhai Patel, Shri Bipinbhai Patel
Petition under Section 86 (1)(a)(b),(f) and (k) of the Electricity Act, 2003 read with Article 12,13 and 17 of
Petition under Section 86 (1)(a)(b),(f) and (k) of the Electricity Act, 2003 read with Article 12,13 and 17 of the Power Purchase Agreement executed dated 26.2.2007 between ESSAR Power Limited and Gujarat Urja Vikas Nigam Limited.
__
3 30/08/2014 11:30 am 1404/2014
Essar Power Gujarat Limited, Essar Power Limited
Essar Power Gujarat Limited, Essar Power Limited
GUVNL
GUVNL
In the matter under section 86 (1) (f) read with 86 (1) (b) of the Electricity Act, 2003 for dispute between a
In the matter under section 86 (1) (f) read with 86 (1) (b) of the Electricity Act, 2003 for dispute between a generating company and the distribution licensee on account of the wrongful deductions carried out by the distribution licensee for the power supplied during the FY 2012-2013.
__