Hearing Schedule
| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 28/08/2014 11:30 am | 1221/2012 |
Vaayu (India) Power Corp. Pvt. Ltd.
Vaayu (India) Power Corp. Pvt. Ltd.
|
GUVNL, GEDA and SLDC
GUVNL, GEDA and SLDC
|
Petition of adjusting the tariff fixed by the Commission in order on determination of tariff for procurement o
Petition of adjusting the tariff fixed by the Commission in order on determination of tariff for procurement of power by dist. Licensees from WEG & other commercial issues dated 30.01.2010 due to petitioner not availing accelerated depreciation.
|
__ |
| 2 | 28/08/2014 11:30 am | 1239/2012 |
Green Infra Corporate Wind Limited
Green Infra Corporate Wind Limited
|
GUVNL
GUVNL
|
Petition for adjustment/enhancement of tariff fixed by the Commission in order on Determination of the tariff
Petition for adjustment/enhancement of tariff fixed by the Commission in order on Determination of the tariff for procurement of power by distribution licensee from wind energy generators and other commercial issues on Order No. 1 of 2010 dated 30.01.2010.
|
__ |
| 3 | 28/08/2014 11:30 am | 1241/2012 |
Green Infra Wind Power Limited
Green Infra Wind Power Limited
|
GUVNL
GUVNL
|
Petition for adjustment / enhancement of, tariff fixed by the Hon'ble Commission in the Order on "Determinatio
Petition for adjustment / enhancement of, tariff fixed by the Hon'ble Commission in the Order on "Determination of the Tariff for Procurement of Power by Distribution Licensees from Wind Energy Generators and other commercial issues" (Order No.1 of 2010) dated 30th January, 2010.
|
__ |
| 4 | 28/08/2014 11:30 am | 1204/2012 |
Land mark Corporation
Land mark Corporation
|
DGVCL
DGVCL
|
Non implementation of the Order passed by the Electricity Ombudsman Ahmedabad in case No. 82 / 2011 up to the
Non implementation of the Order passed by the Electricity Ombudsman Ahmedabad in case No. 82 / 2011 up to the expiry of 30 days period from date of issue of the Order, by the respondent Executive Engineer (O&M) Dakshin Gujarat Vij. Co. Ltd., Surat Urban Division, Pandesara, Surat, hence this petition under clause 3.46 of Consumer Grievances Redressal Forum & Ombudsman Regulation 2011, Notification No. 2 of 2011.
|
__ |
| 5 | 28/08/2014 11:30 am | 1337/2013 |
Solar Semiconductor Power Company (India) Private Limited
Solar Semiconductor Power Company (India) Private Limited
|
GUVNL
GUVNL
|
In the matter of adjudication of disputes under Power Purchase Agreement dated 30.04.2010 and Supplementary Po
In the matter of adjudication of disputes under Power Purchase Agreement dated 30.04.2010 and Supplementary Power Purchase Agreements dated 27.10.2010 and 10.05.2011 between Solar Semiconductor Power Company (India) Private Limited and Gujarat Urja Vikas Nigam Limited under section 86 (1) (f) of the Electricity Act, 2003.
|
__ |
| 6 | 28/08/2014 11:30 am | 1397/2014 |
ACB (India) Limited
ACB (India) Limited
|
GUVNL
GUVNL
|
In the matter of petition under section 86 (1) (f) of the Electricity Act, 2003 read with Article 13 of the Po
In the matter of petition under section 86 (1) (f) of the Electricity Act, 2003 read with Article 13 of the Power Purchase Agreement dated 26.02.2007 executed between Gujarat Urja Vikas Nigam Limited and ACB (India) Limited for adjustment of tariff.
|
__ |
| 7 | 28/08/2014 11:30 am | 1387/2013 |
M/s. Welspun Corp. Limited
M/s. Welspun Corp. Limited
|
PGVCL, GETCO and SLDC
PGVCL, GETCO and SLDC
|
In the matter of filing of petition for illegal recovery of power factor penalty by distribution license and c
In the matter of filing of petition for illegal recovery of power factor penalty by distribution license and consequent refund thereof.
|
__ |
| 8 | 28/08/2014 11:30 am | 1421/2014 |
Steelcast Limited
Steelcast Limited
|
PGVCL and SLDC
PGVCL and SLDC
|
In the matter of filing petition under section 94 of the Electricity Act, 2003 read with Regulation 26.1 of GE
In the matter of filing petition under section 94 of the Electricity Act, 2003 read with Regulation 26.1 of GERC Regulation 2 of 2004, read with Regulation 45 GERC Regulation 3 of 2011 for intra- State Open Access Regulation, 2011, against granting of NOC for Short Term Open Access for the month of May 2014.
|
__ |
| 9 | 28/08/2014 11:30 am | 1430/2014 |
Investment & Precision Casting Limited
Investment & Precision Casting Limited
|
SLDC, GETCO and PGVCL
SLDC, GETCO and PGVCL
|
n the matter of filing petition under section 94 of the Electricity Act, 2003 read with Regulation 26.1 of GER
n the matter of filing petition under section 94 of the Electricity Act, 2003 read with Regulation 26.1 of GERC’s Regulation 2 of 2004 and Regulation 45 of GERC Regulation 3 of 2011 for not grating of NOC for Short Term Open Access (STOA) for the month of June 2014.
|
__ |
| 10 | 28/08/2014 11:30 am | Review Petition No. 1438 of 2014 |
SLDC
SLDC
|
OPGS Power Gujarat Private Limited
OPGS Power Gujarat Private Limited
|
In the matter of filing of Review Petition under section 94 of the Electricity Act, 2003 read with Order 47 Ru
In the matter of filing of Review Petition under section 94 of the Electricity Act, 2003 read with Order 47 Rule 1 of the Code of Civil Procedure, 1908 for review of the order dated 29.04.2014 passed in Petition No. 1386 of 2013 in the matter of True-up for the FY 2012-2013 and determination of tariff for the FY 2014-2015 and Mid-Term Review for the FY 2014-2015 and 2015-2016 of business Plan.
|
__ |
| 11 | 28/08/2014 11:30 am | 1333/2013 |
M/s. Cargo Solar Power Gujarat Private Limited
M/s. Cargo Solar Power Gujarat Private Limited
|
GUVNL
GUVNL
|
In the matter of seeking adjudication of dispute under section 86 (1)(f) of the Electricity Act, 2003 in terms
In the matter of seeking adjudication of dispute under section 86 (1)(f) of the Electricity Act, 2003 in terms of the Power Purchase Agreement dated 30.04.2010 for 25 MW Solar Power Project of M/s Cargo Solar Power Gujarat Pvt. Limited with GUVNL regarding (i) considering the period from 07.04.2012 to 31.07.2013 as Force Majeure Event; and (ii) changes in the definition of Construction Default Date, Schedule Commercial Operation Date (SCOD), Article 2.2 pertaining to Licences, permits and conditions precedents, Article 4.3 pertaining to liquidated damages for delay in commissioning the project/solar thermal grid interconnectivity power plant beyond Schedule Commercial Operation Date and extend the time limit for Schedule Commercial Operation Date from 31.07.2013 to 31.12.2014.
|
__ |
| 12 | 28/08/2014 11:30 am | 1405/2014 |
M/s. Aryan Coal Beneficiation (India) Limited
M/s. Aryan Coal Beneficiation (India) Limited
|
GUVNL, Power Grid Corp. of India, ABB India
GUVNL, Power Grid Corp. of India, ABB India
|
In the matter under section 86 (1) (f) of the Electricity Act, 2003 to direct Respondent No. 1 to refund the l
In the matter under section 86 (1) (f) of the Electricity Act, 2003 to direct Respondent No. 1 to refund the liquidated damages that illegally charged to the Petitioner since no loss was caused to the Respondent No.1.
|
__ |
| 13 | 28/08/2014 11:30 am | 1364/2013 |
M/s. Taxus Infrastructure & Power Projects Private Limited
M/s. Taxus Infrastructure & Power Projects Private Limited
|
GEDA, GUVNL, GETCO, CEI and SLDC
GEDA, GUVNL, GETCO, CEI and SLDC
|
In the matter of filing of petition under section 86(1) (f) of the Electricity Act, 2003 for declaring (i) 5 M
In the matter of filing of petition under section 86(1) (f) of the Electricity Act, 2003 for declaring (i) 5 MW Solar Photo Voltaic (PV) power project set-up by the Petitioner commissioned on 31st March, 2013 instead of 8th August, 2013, (ii) Petitioner is entitled to receive tariff at the rate of Rs. 11.25/kWh instead of Rs. 10.40/kWh paid by the Respondent No. 2 GUVNL and direct the Respondent to pay an amount of Rs. 2,69,86,837 for supply of electricity by the Petitioner from 31st March 2013 to 8th August, 2013 for supply of 23,98,830 kWh and interest on the same as per the Power Purchase Agreement (PPA).
|
__ |
| 14 | 28/08/2014 11:30 am | 1439/2014 |
Torrent Power Limited
Torrent Power Limited
|
|
In the matter of filing of petition under section 94 of Electricity Act, 2003 read with Regulation 58,80,81,82
In the matter of filing of petition under section 94 of Electricity Act, 2003 read with Regulation 58,80,81,82 and 83 of the GERC (Conduct of Business) Regulations, 2004 seeking clarifications/rectifications of the Commission’s Order dated 29.05.2014 in Petition No. 1379 of 2013 for Truing-up of FY 2012-2013 and determination of Tariff for FY 2014-15 for its distribution businesses of Dahej Supply area.
|
__ |
| 15 | 28/08/2014 11:30 am | 1440/2014 |
Gujarat Granito Manufacturer’s Association
Gujarat Granito Manufacturer’s Association
|
SLDC and GETCO
SLDC and GETCO
|
In the matter of filing petition under section 94 of the Electricity Act, 2003 and section 45 read with Regula
In the matter of filing petition under section 94 of the Electricity Act, 2003 and section 45 read with Regulation 6.21 of GERC Regulation 3 of 2011 for intra-State Open Access Regulation, 2011, against STOA transmission charges collected by SLDC for days for which the power is reserved and nontraded in a month under provision of Chapter 6 of GERC Notification for Intra-State Open Access and related matters.
|
__ |
| 16 | 28/08/2014 11:30 am | 1423/2014 |
Mangalam Alloys Limited
Mangalam Alloys Limited
|
GETCO and SLDC
GETCO and SLDC
|
In the matter of filing petition for adjudication of dispute under section 42 (2) and 86 (1) (c) and 3 of the
In the matter of filing petition for adjudication of dispute under section 42 (2) and 86 (1) (c) and 3 of the Electricity Act, 2003 and Regulations 45 and 3 (p) of 2011 of GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 for illegal, arbitrary and discriminatory act of denying NOC for Short Term Open Access in the pretext of non- receipt of consent of STU in feasibility report and strict interpretation of the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011.
|