Hearing Schedule

Hearing Schedule

Sr.No. Date & Time Case No. Petitioner Respondent Subject Matter Previous Hearing Date & Time
1 20/04/2013 11:30 am 1289/2013
MPSEZ Utilities Private Limited
MPSEZ Utilities Private Limited
In the matter of filing a petition for seeking approval for deviations in Standard Bidding Documents issued by
In the matter of filing a petition for seeking approval for deviations in Standard Bidding Documents issued by Ministry of Power, Government of India for long term power procurement for the quantum of 50 (± 20) MW for supply period of FY 2016-2017 to 2040-2041.
__
2 20/04/2013 11:30 am 1290/2013
Saurashtra Cement Limited
Saurashtra Cement Limited
PGVCL and SLDC
PGVCL and SLDC
In the matter of denial of consent for Open Access by the Distribution Licensee under the Gujarat Electricity
In the matter of denial of consent for Open Access by the Distribution Licensee under the Gujarat Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) Regulations, 2011, Notification No. 3 of 2011.
__
3 20/04/2013 11:30 am 1292/2013
Essar Power Gujarat Limited
Essar Power Gujarat Limited
GUVNL
GUVNL
In the matter of determination of Petition fees payable in accordance with Regulation 30 (2) of the Gujarat El
In the matter of determination of Petition fees payable in accordance with Regulation 30 (2) of the Gujarat Electricity Regulatory Commission (Conduct of Business) Regulations, 2004 read with Regulation 3 (i) of Gujarat Electricity Regulatory Commission (Fees, Fines and Charges) Regulations, 2005.
__
4 20/04/2013 11:30 am 1297/2013
Under Secretary, EPD, Govt. of Gujarat
Under Secretary, EPD, Govt. of Gujarat
Torrent Power Limited
Torrent Power Limited
In the matter of tariff for Agrocultural Consumers of Torrent Power Limited (Ahmedabad Unit).
In the matter of tariff for Agrocultural Consumers of Torrent Power Limited (Ahmedabad Unit).
__
5 20/04/2013 11:30 am 1293/2013
M/s. Shri Hari Om Agro Food Processors
M/s. Shri Hari Om Agro Food Processors
DE (O&M) DGVCL
DE (O&M) DGVCL
In the matter of non-implementation of the order passed by the Electricity Ombudsman, Ahmedabad in Case No. 88
In the matter of non-implementation of the order passed by the Electricity Ombudsman, Ahmedabad in Case No. 88/2012 up to the expiry of 30 days period from date of receipt of the order by the respondent DGVCL, under clause 3.46 of Consumer Grievances Redressal Forum & Ombudsman Regulation, 2011, Notification No. 2 of 2011.
__
6 20/04/2013 11:30 am 1296/2013
Essar Power Gujarat Limited
Essar Power Gujarat Limited
GUVNL
GUVNL
In the matter of adjustment of tariff under Article 13 of the Power Purchase Agreement dated 26.02.2007 entere
In the matter of adjustment of tariff under Article 13 of the Power Purchase Agreement dated 26.02.2007 entered into the Gujarat Urja Vikas Nigam Limited and Essar Power Gujarat Limited
__
7 20/04/2013 11:30 am 1282/2013
Kaizen Switchgear Products
Kaizen Switchgear Products
MGVCL and GETCO
MGVCL and GETCO
Petition Under Section 86 (1) (c) and (f) of the Electricity Act, 2003.
Petition Under Section 86 (1) (c) and (f) of the Electricity Act, 2003.
__
8 20/04/2013 11:30 am 1204/2012
M/s. Landmark Corporation
M/s. Landmark Corporation
EE (O&M), DGVCL
EE (O&M), DGVCL
Non implementation of the Order passed by the Electricity Ombudsman Ahmedabad in case No. 82 / 2011 up to the
Non implementation of the Order passed by the Electricity Ombudsman Ahmedabad in case No. 82 / 2011 up to the expiry of 30 days period from date of issue of the Order, by the respondent Executive Engineer (O&M) Dakshin Gujarat Vij. Co. Ltd., Surat Urban Division, Pandesara, Surat, hence this petition under clause 3.46 of Consumer Grievances Redressal Forum & Ombudsman Regulation 2011, Notification No. 2 of 2011.
__
9 20/04/2013 11:30 am 1257/2012
M/s. Essar Power Gujarat Ltd.
M/s. Essar Power Gujarat Ltd.
GUVNL and GETCO
GUVNL and GETCO
Petition under section 86(1)(f) of the Electricity Act,2003 read with article 17 of the Power Purchase Agreeme
Petition under section 86(1)(f) of the Electricity Act,2003 read with article 17 of the Power Purchase Agreement dated 26.02.2007 executed between Essar Power Ltd. and Gujarat Urja Vikas Nigam Ltd.
__
10 20/04/2013 11:30 am 1259/2012
Essar Steel India Limited
Essar Steel India Limited
DGVCL, SLDC, NLDC, NRLDC, WRLDC, and Essar Electric Power Development Corporation Limited
DGVCL, SLDC, NLDC, NRLDC, WRLDC, and Essar Electric Power Development Corporation Limited
Petition under section 86 (1) (a) of the Electricity Act, 2003 with Regulation 32
Petition under section 86 (1) (a) of the Electricity Act, 2003 with Regulation 32
__
11 20/04/2013 11:30 am 1188/2012
Solar Semiconductor Power Company (India) Pvt. Ltd.
Solar Semiconductor Power Company (India) Pvt. Ltd.
GUVNL, GEDA and EPD
GUVNL, GEDA and EPD
Petition under regulation 80 of the GERC (Conduct of Business) Regulations, 2004 read with section 86 of the E
Petition under regulation 80 of the GERC (Conduct of Business) Regulations, 2004 read with section 86 of the Electricity Act, 2003 for extension of the “Control Period” as defined by the Commission through its Tariff Order dated 29.01.2010, passed in Order No. 2 of 2010.
__
12 20/04/2013 11:30 am 1180/2011
M/s. Sunkon Energy Private Limited
M/s. Sunkon Energy Private Limited
GUVNL, GEDA and EPD
GUVNL, GEDA and EPD
Petition under regulation 80 of the GERC (Conduct of Business) Regulations, 2004 read with section 86 of the E
Petition under regulation 80 of the GERC (Conduct of Business) Regulations, 2004 read with section 86 of the Electricity Act, 2003 for extension of the “Control Period” as defined by the Commission through its Tariff Order dated 29.01.2010, passed in Order No. 2 of 2010.
__
13 20/04/2013 11:30 am 1299/2013
M/s. British Super Alloys Private Limited
M/s. British Super Alloys Private Limited
Uttar Gujarat Vij Company Limited
Uttar Gujarat Vij Company Limited
In the matter under section 86 (1) (a), (b), (e) and (f) of the Electricity Act, 2003 for adjudication of the
In the matter under section 86 (1) (a), (b), (e) and (f) of the Electricity Act, 2003 for adjudication of the dispute between the Licensee and Generating Company and for the decision that the petitioner is entitled for the Tariff of Rs. 3.37 /- per Unit without 15 % deduction for surplus energy sale after captive use in the Wheeling Agreement with the respondent (UGVCL) as the WTG was commissioned during the control period of GERC Order No.2 of 2006 dated 11/8/2006 read with the original Wind Policy 2007 dated 13/6/2007 and for issuing further direction to UGVCL to revise the amended Agreement dated 16/7/2011 accordingly and for issuing further direction to UGVCL not to apply rate of 85% of Rs.3.37 per Unit and also for further direction to UGVCL for refund of the amount of 15 % deducted up-till now and also for further direction to UGVCL to give set-off of wheeled energy generation for the month of March 2011 which is not given though the WTG was purchased by the petitioner in the month of March 2011 and the Wheeling Agreement was signed on 31/3/2011 by the petitioner and UGVCL.
__
14 20/04/2013 15:30 pm 1002/2010
Essar Power Limited
Essar Power Limited
GUVNL
GUVNL
Petition for adjudication of the disputes with respect to the monetary claims of the petitioner against the re
Petition for adjudication of the disputes with respect to the monetary claims of the petitioner against the respondent under the Power Purchase Agreement dated 30th May, 1996.
__