Hearing Schedule
| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 05/03/2013 11:30 am | 1204/2012 |
Land mark Corporation
Land mark Corporation
|
DGVCL
DGVCL
|
Non-implementation of the order of the ombudsman
Non-implementation of the order of the ombudsman
|
__ |
| 2 | 05/03/2013 11:30 am | 1282/2013 |
Kaizen Switchgear Products
Kaizen Switchgear Products
|
MGVCL and GETCO
MGVCL and GETCO
|
Petition of 86(1)(C) and (f) of the Electricity Act, 2003.
Petition of 86(1)(C) and (f) of the Electricity Act, 2003.
|
__ |
| 3 | 05/03/2013 11:30 am | 1205/2012 |
Kindle Engineering & Construction Pvt. Ltd.
Kindle Engineering & Construction Pvt. Ltd.
|
TPL
TPL
|
In the matter under regulation 80 of the GERC reg. 2004 readwith section 86(1)(b) of E.A., 2003, for approval
In the matter under regulation 80 of the GERC reg. 2004 readwith section 86(1)(b) of E.A., 2003, for approval of PPA
|
__ |
| 4 | 05/03/2013 11:30 am | 1246/2012 |
Shri Renuka Sugars Ltd.
Shri Renuka Sugars Ltd.
|
GETCO & PGVCL
GETCO & PGVCL
|
Petition under regulation 80 of GERC (Conduct of petitioner) Regulation, 2004 read with section 86 of the EA,
Petition under regulation 80 of GERC (Conduct of petitioner) Regulation, 2004 read with section 86 of the EA, 2003
|
__ |
| 5 | 05/03/2013 11:30 am | 1259/2012 |
Essar Steel India Ltd.
Essar Steel India Ltd.
|
DGVCL, SLDC, NLDC, NRLDC, WRLDC, Essar Electric Power Development Corp. Ltd.
DGVCL, SLDC, NLDC, NRLDC, WRLDC, Essar Electric Power Development Corp. Ltd.
|
Petition u/s. 86(1) (a) of the EA 2003 r/w regulations 32 of the GERC (Terms and Conditions of Intra-State Ope
Petition u/s. 86(1) (a) of the EA 2003 r/w regulations 32 of the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 and Regulation 8 of the GERC (Electricity Supply Code and Related Matters/ Regulations 2005 for declaration and waiver of demand charges.
|
__ |
| 6 | 05/03/2013 11:30 am | 1273/2013 |
Meena Agency Ltd.
Meena Agency Ltd.
|
PGVCL and GETCO
PGVCL and GETCO
|
Petition under clauses (a), (b) , (e) and (f) of sub-section of Section 86 of the EA, 2003 and arbitrary claus
Petition under clauses (a), (b) , (e) and (f) of sub-section of Section 86 of the EA, 2003 and arbitrary clause (6) of wheeling agreement entered into with PGVCL dated 28.04.2010, treatment of wind energy generation units injected in the grid from the date of Commissioning of wind turbine generator vide letter of GEDA dated 12.10.2009 to the date of signing agreement with PGVCL and set-ff wind energy generation units injected in the grid against commissioning to be given from the date of commissioning of WTGs and commercial settlement mechanism for treatment to excess injection during the respective months.
|
__ |
| 7 | 05/03/2013 11:30 am | 1274/2013 |
Navrang Colour Lab
Navrang Colour Lab
|
DE, PGVCL and CE, PGVCL
DE, PGVCL and CE, PGVCL
|
Disconnection of electricity supply against sec. 56 and penalty u/s. 142 of EA, 2003 and regulations 64 of GER
Disconnection of electricity supply against sec. 56 and penalty u/s. 142 of EA, 2003 and regulations 64 of GERC Conduct of Business Regulations ,2005 and other provisions rules and regulations made under EA, 2003.
|
__ |