| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 11/12/2012 11:30 am | 1221/2012 |
Vaayu (India) Power Corp. Pvt. Ltd.
Vaayu (India) Power Corp. Pvt. Ltd.
|
GUVNL, GEDA and SLDC
GUVNL, GEDA and SLDC
|
Petition of adjusting the tariff fixed by the Commission in order on determination of tariff for procurement o
Petition of adjusting the tariff fixed by the Commission in order on determination of tariff for procurement of power by dist. Licensees from WEG & other commercial issues dated 30.01.2010 due to petitioner not availing accelerated depreciation.
|
__ |
| 2 | 11/12/2012 11:30 am | 1239/2012 |
Green Infra Corporate Wind Limited
Green Infra Corporate Wind Limited
|
GUVNL
GUVNL
|
Petition for adjustment/enhancement of tariff fixed by the Commission in order on Determination of the tariff
Petition for adjustment/enhancement of tariff fixed by the Commission in order on Determination of the tariff for procurement of power by distribution licensee from wind energy generators and other commercial issues on Order No. 1 of 2010 dated 30.01.2010.
|
__ |
| 3 | 11/12/2012 11:30 am | 1241/2012 |
Green Infra Wind Power Limited
Green Infra Wind Power Limited
|
GUVNL
GUVNL
|
Petition for adjustment / enhancement of, tariff fixed by the Hon'ble Commission in the Order on "Determinatio
Petition for adjustment / enhancement of, tariff fixed by the Hon'ble Commission in the Order on "Determination of the Tariff for Procurement of Power by Distribution Licensees from Wind Energy Generators and other commercial issues" (Order No.1 of 2010) dated 30th January, 2010.
|
__ |
| 4 | 11/12/2012 11:30 am | 1252/2012 |
Regen Power Tech Pvt. Ltd.
Regen Power Tech Pvt. Ltd.
|
GETCO
GETCO
|
To pass appropriate urgent orders and/or directions to extend the time period granted to the Petitioner by the
To pass appropriate urgent orders and/or directions to extend the time period granted to the Petitioner by the Commission vide its Order dated 16.8.2012 for commissioning of the Sub Station of 66/33 kV providing Power Evacuation Facility to wind energy based renewable energy power Project with a capacity of 35 MW at Khareda, Morbi Taluk, Rajkot District, Gujarat Khareda, for a further period of 3 (Three) months (from 25th October, 2012 to 25th January, 2013) and to restrain the respondent from encashing the Bank Guarantee provided by the Petitioner.
|
__ |
| 5 | 11/12/2012 11:30 am | 1253/2012 |
Regen Power Tech Pvt. Ltd.
Regen Power Tech Pvt. Ltd.
|
GETCO
GETCO
|
To pass appropriate urgent orders and/or directions to extend the time period granted to the Petitioner by the
To pass appropriate urgent orders and/or directions to extend the time period granted to the Petitioner by the Commission vide its Order dated 16.8.2012 for commissioning of the Sub Station of 66/33 kV providing Power Evacuation Facility to wind energy based renewable energy power Project with a capacity of 35 MW at Vejalpar, Maliya Taluk, Rajkot District, Gujarat, for a further period of 3 (Three) months (from 25th October, 2012 to 25th January, 2013) and to restrain the respondent from encashing the Bank Guarantee provided by the Petitioner.
|
__ |
| 6 | 11/12/2012 11:30 am | 1254/2012 |
Under Secretary Industries & Mines, Dept. Government of Gujarat, Sachivalaya, G’nagar.
Under Secretary Industries & Mines, Dept. Government of Gujarat, Sachivalaya, G’nagar.
|
GUVNL, TPL, UGVCL, MGVCL, DGVCL & PGVCL
GUVNL, TPL, UGVCL, MGVCL, DGVCL & PGVCL
|
U/s. 65 of EA, 2003 for providing power tariff subsidy @ Rs. 1/unit I the billed amount of the utilities for t
U/s. 65 of EA, 2003 for providing power tariff subsidy @ Rs. 1/unit I the billed amount of the utilities for the cotton spinning industries & weaving units with & without preparatory in the state as per para 5.4 of the Guj. Textile Policy, 2012 declare vide Industries & Mines Dept. GR No. TEX-1-2-12-65117-T dated 5.09.2012 and to compensate the amount to the Discoms/Utilities.
|
__ |
| 7 | 11/12/2012 11:30 am | 1257/2012 |
Essar Power Gujarat Pvt. Ltd.
Essar Power Gujarat Pvt. Ltd.
|
GETCO & GUVNL
GETCO & GUVNL
|
Petition u/s. 86 (1) (f) of EA, 2003 read with Article 17 of the PPA dated 26.02.2007 executed between Essar P
Petition u/s. 86 (1) (f) of EA, 2003 read with Article 17 of the PPA dated 26.02.2007 executed between Essar Power Guj. Pvt. Ltd. & GUVNL.
|
__ |
| 8 | 11/12/2012 11:30 am | 1246/2012 |
Shri Renuka Sugars Ltd.
Shri Renuka Sugars Ltd.
|
GETCO & PGVCL
GETCO & PGVCL
|
Petition under regulation 80 of GERC (Conduct of petitioner) Regulation, 2004 read with section 86 of the EA,
Petition under regulation 80 of GERC (Conduct of petitioner) Regulation, 2004 read with section 86 of the EA, 2003
|