Hearing Schedule
| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 20/10/2012 11:30 am | 1247/2012 |
M/s. Millenium Synergy (Guj) Pvt.Ltd.
M/s. Millenium Synergy (Guj) Pvt.Ltd.
|
GUVNL
GUVNL
|
Adjudication of dispute under PPA dated 29.05.2010 u/s. 86(1) r/w 86(1)(e) of E.A. 2003 between both the parti
Adjudication of dispute under PPA dated 29.05.2010 u/s. 86(1) r/w 86(1)(e) of E.A. 2003 between both the parties.
|
__ |
| 2 | 20/10/2012 11:30 am | 1248/2012 |
ESP Urja Pvt. Ltd.
ESP Urja Pvt. Ltd.
|
GUVNL
GUVNL
|
Adjudication of dispute under PPA dated 31.05.2010 u/s. 86(1) r/w 86(1)(e) of E.A. 2003 between both the parti
Adjudication of dispute under PPA dated 31.05.2010 u/s. 86(1) r/w 86(1)(e) of E.A. 2003 between both the parties.
|
__ |