Hearing Schedule
| Sr.No. | Date & Time | Case No. | Petitioner | Respondent | Subject Matter | Previous Hearing Date & Time |
|---|---|---|---|---|---|---|
| 1 | 07/02/2012 11:30 am | 1173/2011 |
Videocon Industries Ltd.
Videocon Industries Ltd.
|
GETCO & DGVCL
GETCO & DGVCL
|
Review petition in order No. 256/2003 and 867/2006
Review petition in order No. 256/2003 and 867/2006
|
__ |
| 2 | 07/02/2012 11:30 am | 1174/2011 |
GETCO
GETCO
|
Adani Power Ltd. and GUVNL
Adani Power Ltd. and GUVNL
|
Review petition in order No. 1093/2011
Review petition in order No. 1093/2011
|
__ |
| 3 | 07/02/2012 11:30 am | 1131/2011 |
M/s.Gujarat Ambuja Export Ltd.,
M/s.Gujarat Ambuja Export Ltd.,
|
Uttar Gujarat Vij Company Limited (UGVCL)
Uttar Gujarat Vij Company Limited (UGVCL)
|
Dispute regarding levy of wheeling charges and wheeling losses against the provisions of Order No.1 of 2010 da
Dispute regarding levy of wheeling charges and wheeling losses against the provisions of Order No.1 of 2010 dated 30th January,2010.
|
__ |
| 4 | 07/02/2012 11:30 am | 1130/2011 |
Gujarat State Electricity Corporation Ltd.
Gujarat State Electricity Corporation Ltd.
|
Gujarat Urja Vikas Nigam Limited (GUVNL)
Gujarat Urja Vikas Nigam Limited (GUVNL)
|
Petition for approval of Capital Cost for 75 MW Kutch Lignite Thermal Power Station Unit No.4 (KLTPS-4) in res
Petition for approval of Capital Cost for 75 MW Kutch Lignite Thermal Power Station Unit No.4 (KLTPS-4) in respect to the PPA between GSECL and GUVNL.
|
__ |
| 5 | 07/02/2012 11:30 am | 1188/2012 |
Solar Semiconductor Power Company (India) Private Limited
Solar Semiconductor Power Company (India) Private Limited
|
GUVNL, GEDA and EPD, GoG
GUVNL, GEDA and EPD, GoG
|
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff or
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff order dated 29th January, 2010 in order No. 2 of 2010.
|
__ |
| 6 | 07/02/2012 11:30 am | 1189/2012 |
Sun Clean Renewable Power Pvt. Ltd.
Sun Clean Renewable Power Pvt. Ltd.
|
GEDA, GUVNL and EPD,GoG
GEDA, GUVNL and EPD,GoG
|
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff or
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff order dated 29th January, 2010 in order No. 2 of 2010.
|
__ |
| 7 | 07/02/2012 11:30 am | 1190/2012 |
Toss Financial Services Pvt. Ltd.
Toss Financial Services Pvt. Ltd.
|
GUVNL, GEDA and EPD, GoG
GUVNL, GEDA and EPD, GoG
|
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff or
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff order dated 29th January, 2010 in order No. 2 of 2010.
|
__ |
| 8 | 07/02/2012 11:30 am | 1191/2012 |
AES Solar Energy Gujarat Pvt. Ltd.
AES Solar Energy Gujarat Pvt. Ltd.
|
EPD, GoG, GEDA, GUVNL, GPCL and GETCO
EPD, GoG, GEDA, GUVNL, GPCL and GETCO
|
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff or
In the matter of petition for extension of “Control Period” as defined by the Commission through tariff order dated 29th January, 2010 in order No. 2 of 2010.
|
__ |