6:00 am

1750/2018

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter of the Petition for grant of sanction for commissioning of 1 MW Solar Power Plant as a special case at Vadodara.

Find out more »

1769/2018

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter filing of petition under section 142 and 146 read with Section 149 of Electricity Act 2003 for non-compliance of Electricity Ombudsman’s order and violation of the Regulation.

Find out more »

1770/2018

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter of Petition under section 129 of the Electricity Act, 2003 read with Regulation 62 (b) of GERC (Conduct of Business) Regulations, 2004 for seeking order through appropriate directions for securing compliance by the licensee which has contravened certain provisions contained in Notification No. 5/2016 GERC (Net Metering Rooftop Solar PV Grid Interactive … Continue reading "1770/2018"

Find out more »

1774/2018

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter filing of petition under section 19, 142, 146 and 149 of Electricity Act 2003 for initiation of action against MGVCL for non-compliance of Electricity Ombudsman’s order and violation of the Regulation.

Find out more »

1780/2019

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter filing of petition under section 129, 146 and 149 read with Regulation 62 (b) of the GERC (Conduct of Business) Regulations, 2004 seeking order through appropriate direction for securing compliance by the licensees which has contravened certain provisions contained in GERC (Net Metering Rooftop Solar PV Grid Interactive Systems) Regulations, 2016 issued … Continue reading "1780/2019"

Find out more »

1418/2014

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter of filing petition for approval of purchase of power to be generated from Rooftop Solar Power Generation Projects at 14 different sites by Surat Municipal Corporation aggregating to installed capacity of 750 KWp on a Long-Term basis at the tariff to be determined by the GERC under section 86 (1) (b) read … Continue reading "1418/2014"

Find out more »

1643/2017 & 1644/2017

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

Petition for deciding the maintainability and admissibility of the Petitions submitted by TPL in absence of details and documents under GERC (Conduct of Business) Regulations, 2004, Fees, fines and charges Regulations 2005 read with Section 61, 62, 64, 86 (a) (b), 86 (2), 94, 142, 146, 149 of the Electricity Act, 2003 r/w GERC (MYT) … Continue reading "1643/2017 & 1644/2017"

Find out more »

1735/2018 & 1736/2018

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

Review Petition under Section 94(1)(f) of Electricity Act, 2003 read with Clause-72(1) of GERC (Conduct of Business) Regulations, 2004 in the matter of GERC Order dated 30/01/2018 (Date of Hearing 12/01/2018) in the matter of Petition Nos. 1643 of 2017 & 1644 of 2017 submitted by Utility Users’ Welfare Association and others

Find out more »

1794/2019

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter of filing of Petition under Section 86 (1) (b) of the Electricity Act, 2003 seeking approval of the Commission for procurement of power on “As and When required basis” from 165 MW GIPCL Station – II for a period of 5 years and approval of Power Purchase Agreement dated 29.03.2019.

Find out more »

1782/2019

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter filing of petition under Section 142 and 146 read with Section 149 of Electricity Act 2003 for non-compliance of Electricity Ombudsman’s order and violation of the Regulation.

Find out more »

1783/2019

May 24, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter filing of petition for non-compliance of Electricity Ombudsman’s order, violation of the Regulations and earnestly requesting action by the Commission under Sections 142 and 146 read with Section 149 of Electricity Act 2003.

Find out more »