Events Search and Views Navigation
6:00 am
1111/2011
Application for the grant of additional load on 22 KV supply by differentiating the maximum contract demand limitation between 11 KV and 22 KV.
Find out more »1110/2011
Review petition against the order of the Commission dated 23.12.2010 in Misc. Application No. 14 of 2010.
Find out more »10:00 am
1107/2011
Review petition in the order dated 9/12/2009 in petition no. 966 of 2009 filed by TPL under section 62 of EA, 2003 readwith GERC (Terms & Conditions of Tariff Regulations) 2005 and MYT regulations 2007 for APR for FY 2008-09 and ARR for 2009-10 for their generation and distribution business under MYT control period 2008-09 … Continue reading "1107/2011"