2481/2025 & IA No. 80/2025

April 7 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 of EA 2003 read with Order No. 01 of 2024 dated 22.02.2024 ‘Tariff Framework for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects Including Storage, if any, and other Commercial issues for the State of Gujarat’ passed by the Commission, seeking extension of the Scheduled Date of Commissioning of infrastructure being developed by the Petitioner for evacuation of power from its 40 MW Hybrid Power Plant to GETCO’s 66 kV Sutrapada Sub-Station on account of occurrences and circumstances beyond the reasonable control of the Petitioner being Unforeseen events or reasons.