2226/2023

February 23 @ 6:00 am - 11:30 am UTC+5.5

In the matter of Petition under Section 86 of the Electricity Act, 2003 read with Clause 16 of the Procedure for ‘Grant of Connectivity to projects based on Renewable Sources to Intra-State Transmission System’ approved by the Commission on 07.01.2023 and Connection Agreement dated 24.07.2023 executed between Enfinity Global Surya Vayu Energy Pvt. Ltd., and GETCO, seeking to quash and set aside the Letter dated 16.09.2023 issued by GETCO and for directions to restore the Stage-II Connectivity dated 31.05.2023 granted to Enfinity Global Surya Vayu Energy Pvt. Ltd.

Details

Date:
February 23
Time:
6:00 am - 11:30 am UTC+5.5
Event Category: