1364/2013

January 10, 2014 @ 6:00 am - 12:30 pm UTC+5.5

In the matter of filing of petition under section 86(1) (f) of the Electricity Act, 2003 for declaring (i) 5 MW Solar Photo Voltaic (PV) power project set-up by the Petitioner commissioned on 31st March, 2013 instead of 8th August, 2013, (ii) Petitioner is entitled to receive tariff at the rate of Rs. 11.25/kWh instead of Rs. 10.40/kWh paid by the Respondent No. 2 GUVNL and direct the Respondent to pay an amount of Rs. 2,69,86,837 for supply of electricity by the Petitioner from 31st March 2013 to 8th August, 2013 for supply of 23,98,830 kWh and interest on the same as per the Power Purchase Agreement (PPA).