Loading Events

« All Events

  • This event has passed.

1429 of 2014 & I.A. No. 2 of 2018

July 20, 2019 @ 6:00 am - 12:30 pm UTC+5.5

In the matter of petition under Section 86 (1) (f) of the Electricity Act, 2003 for unlawful recovery of Parallel Operation Charges by PGVCL qua Essar Oil Limited’s Captive Power Plant operating in parallel with GETCO’s grid for the period from 13.09.2006 till 01.06.2011

Details

Date:
July 20, 2019
Time:
6:00 am - 12:30 pm UTC+5.5
Event Category: