2654/2026 & allied IAs
May 29 @ 6:00 am - 11:30 am UTC+5.5
Petition under Section 86 of the Electricity Act, 2003 read with Regulation 80 & 82 GERC (Conduct of Business) Regulations, 2004, read with Gujarat Renewable Energy Policy, 2023 & amendments thereof and the Tariff Order dated 31.08.2024 praying before the Commission to exercise its powers under Section 86 of the Electricity Act, 2003 and direct the Respondent Gujarat Energy Transmission Corporation Limited to grant extension of time for commissioning of the Evacuation Line along with bays and metering system and connectivity of the transmission line and thereby grant
extension of time in executing the 101 MW Solar Project.