2559/2025

April 7 @ 6:00 am - 11:30 am UTC+5.5

Petition under Section 86 (1) (f) of EA, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations, 2004 for connectivity Agreement dated 14.11.2024 between M/s. Star Pipe Foundry (India) Pvt. Ltd. And GETCO for establishing connectivity of 20 MW Solar Power plant at Amreli to GETCO’s transmission at 66 kV level with 66 kV Nagadhara Sub-station of GETCO and Petition for seeking extension of time limit for a period of 1 year i.e., upto 30.09.2026 for commissioning of the balance 9 MW capacity of Star Pipe’s 20 MW Solar Power Plant at Amreli due to
unforeseen and uncontrollable events.