2472/2025 & IA No. 31/2025
June 26, 2025 @ 6:00 am - 11:30 am UTC+5.5
Petition filed under Sections 86(1)(f), 86 (1)(c) & (e) and other applicable provisions of EA, 2003 r/w. Regulations 80 & 82 of GERC (Conduct of Business Regulations, 2004 seeking extension of time period for construction of evacuation infrastructure till 31.12.2025 & for use of spare 220 kV Bay at 220 kV Kalawad substation on temporary basis until 31.12.2025 & for granting the rightful time to Petitioner for commissioning of entire capacity of 25 MW of Wind-Solar Hybrid Power at 220 kV Kalawad S/s as per procedure for “Grant of Connectivity to Projects based on Renewable Sources to Intra-State Transmission System” dated 07.01.2023.