- This event has passed.
1826/2019 & allied IA
October 16 @ 6:00 am - 11:30 am UTC+5.5
In the matter of Petition under Sections 42, 43, 50, 86 & other applicable provisions of the Electricity Act, 2003 read with GERC (Electricity Supply Code and Related Matters) Regulations, 2015, GERC (Standard of Performance of Distribution Licensee) Regulations, 2005 and other applicable Regulations of the Commission seeking additional time for completion of 66 kV transmission line for 5000 KVA contract demand and consequently directing MGVCL to suspend two months’ notice dated 14.08.2019 issued to the Petitioner for levying demand charges on such contract demand on deemed release basis.