| 1024/2010 (under Remand Proceedings) |
06-11-2026 |
M/s Tarini Infrastructure Limited |
GUVNL & Ors. |
Petition for fixation of tariff for two small hydro power projects of 3 MW and 2.6 MW at Daman Ganga Dam/ Madhuban Reservoir under Section 62 read with Section 86(1)(a) of the Electricity Act,2003. |
View PDF
|
| 2673/2026 |
06-11-2026 |
Caspian Renewables Private Limited |
GUVNL |
Petition under Section 86(1) (f) of the Electricity Act, 2003 read with Articles 3.3, 8.1 and 8.2 of the Power Purchase Agreement dated 02.07.2024 seeking extension of the Scheduled Commencement of supply Date on account of force majeure events and other events beyond the Petitioner’s reasonable control, together with consequential contractual reliefs. |
View PDF
|
| 1868/2020 |
06-11-2026 |
GUVNL |
M/s Junagadh WTE Pvt. Limited |
Petition under Section 86 of the Electricity Act, 2003 recovery of compensation as liquidated damages for termination of the Power Purchase Agreement dated 26.10.2017 for default under PPA. |
View PDF
|
| 2698/2026 |
05-11-2026 |
Tata Power Renewables Energy Limited |
SLDC & Ors. |
Interlocutory Application under Section 94 (2) of the Electricity Act, 2003 read with Regulation 61 of the GERC (Conduct of Business) Regulations, 2004 seeking interim reliefs. |
View PDF
|
| 2697/2026 |
05-11-2026 |
Tata Power Renewables Energy Limited |
SLDC & Ors. |
Interlocutory Application under Regulation 61 of the GERC (Conduct of Business) Regulations, 2004 seeking interim reliefs. |
View PDF
|
| 2692/2026 |
05-11-2026 |
T. P. Kirnali Limited & T. P. Saurya Limited |
SLDC & Ors. |
Interlocutory Application seeking interim reliefs. |
View PDF
|
| 2054/2022 |
05-11-2026 |
Ravi Kiran Solar Plant |
GUVNL & Ors. |
Petition for considering the Old Solar Policy for signing of the wheeling agreement for 1.79 MW Solar Power Plant. |
View PDF
|
| 2728/2026 |
04-11-2026 |
GIFT Power Company Limited |
|
Petition under Sections 63 and 86 of the Electricity Act, 2003 for seeking approval of releasing Request for Selection (RfS) document for Procurement of 10 MW RTC Renewable Energy with upto “100% Greenshoe Option” from Intra-State Grid Connected RE Projects and seeking approval of appropriate deviations under Clause 3.1.1 and Clause 17 of the Guidelines for Tariff based Competitive Bidding Process for Procurement of Firm and Dispatchable Power from Grid Connected Renewable Energy Power Projects with Energy Storage systems notified by Ministry of Power on 9th June 2023 and as per the Amendments issued from time to time. |
View PDF
|
| 2682/2026 |
04-11-2026 |
M/s. Jamnagar Renewables Two Pvt. Limited & Others |
GETCO |
Petition under Sections 86 (1) (f) and (k) of the Electricity Act, 2003 read with Regulation 17.9 and Regulation 29 of the GERC (Terms and Conditions for Green Energy Open Access) Regulations, 2024 and Regulation 80 of the GERC (Conduct of Business) Regulations, 2004, seeking directions to GETCO to accept Bank Guarantee as a valid Payment Security Mechanism for grant and continuance of Medium Term Open Access. |
View PDF
|
| 2691/2026 |
03-11-2026 |
Martial Solren Private Limited |
GUVNL & Ors. |
Petition under Section 86 (1) of the Electricity Act, 2003 read with provisions of the GERC (Gujarat Electricity Code) Regulations, 2013 and CERC (Indian Electricity Code) Regulations 2023 seeking issuance of the directions to GETCO and GUVNL to
compensate the Petitioner for loss in revenue attributable to generation loss suffered by arbitrary curtailment/backing down instructions issued by GETCO. |
View PDF
|