1496 of 2015 31-07-2026 Kejriwal Industries GETCO & SLDC Petition under Sections 142 and 146 of the Electricity Act, 2003 read with Section 42 (2) of the Electricity Act, 2003 and Regulations 3 (p) and 45 of the GERC (Terms and Conditions of Intra-State Open Access) Regulations, 2011 for non-compliance of the Order of Commission dated 16.01.2015 in the Petition No. 1407 of 2014 and others by the Respondents. View PDF
2685/2026 30-07-2026 GUVNL Petition for approval of Short-Term Arrangement of Power pursuant to selection of successful bidders through DEEP Portal of Ministry of Power, Government of India, for the period from 01.08.2026 to 31.03.2027 and the Commission’s Guidelines dated 14.08.2013 View PDF
1992/2021 29-07-2026 Deendayal Port Authority Petition under the GERC (Procurement of Energy from Renewable Sources) Regulations, 2010 and its subsequent amendments thereto for revision of Renewable Power Purchase Obligation (RPO) for FY 2019-20. View PDF
1875/2020 23-07-2026 GIFT Power Company Ltd. UGVCL & others Petition under Section 50 of the Electricity Act, 2003 and Clauses 3.3, 9.21, 9.22, 9.23, 9.24 and 9.25 of GERC (Electricity Supply Code and Related matters) Regulations, 2015 for approval and necessary direction of the Commission with regard to proposal of GIFT Power Company Limited for modification in the billing and metering arrangement of HTP-I consumers residing in the High-rise buildings in its area of supply. View PDF
2003/2021 23-07-2026 GIPCL GUVNL Petition under Section 86 of the Electricity Act, 2003 read with Article 9 of the Power Purchase Agreement dated 26.08.2019 executed between GIPCL and GUVNL seeking approval for compensation due to Change in Law Event being imposition of Safeguard Duty having its direct effect on the project Cost. View PDF
2092/2022 23-07-2026 Virgo Aluminum Limited MGVCL & GETCO Petition under Sections 42, 43, 50, 86 and other applicable provisions of the Electricity Act, 2003 read with GERC (Electricity Supply Code and Related Matters) Regulations, 2015, GERC (Standard of Performance of Distribution Licensee) Regulations 2005 and other applicable Regulations of the GERC for seeking deemed extension of time for completion of 66 KV transmission line for 5000 KVA contract demand on post-facto basis and consequently directing MGVCL to consider 60 days’ notice period from the deemed extended date and to refund minimum demand charges levied by MGVCL on deemed release basis on 5000 KVA contract demand till physical release of connection. View PDF
1862/2020 23-07-2026 Surya Roshni Limited GETCO & PGVCL Petition for extension of time limit for erection of the 66 KV transmission line for enhancement of the load from 4000 KVA to 7000 KVA. View PDF
2473/2025 23-07-2026 Renewgain Private Limited GETCO Petition under Section 86 (1) (c), (e) and (f) of the Electricity Act, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations, 2004 seeking directions for quashing the letter dated 18.02.2025 issued at the behest of Respondent GETCO and for seeking further extension. View PDF
1826/2019 along with IAs 22-07-2026 J. K. Cement Limited MGVCL & GETCO Petition under Section 42, 43, 50, 86 and other applicable provisions of the Electricity Act, 2003 read with GERC (Electricity Supply Code and Related Matters) Regulations, 2015, GERC (Standard of Performance of Distribution Licensee) Regulations, 2005 and other applicable Regulations of the Commission seeking to grant additional time for completion of 66 kV transmission line for 5000 KVA Contract Demand and consequently directing MGVCL to suspend the Two months’ notice (TMN) dated 14.08.2019 issued to the Petitioner for levying demand charges on contract demand 5000 KVA on deemed release basis. View PDF
2655/2026 20-07-2026 VMS TMT Limited GETCO Petition under Section 86 (1) (f) (c) & (e) and other applicable provisions of the Electricity Act, 2003 read with read with Regulations 80 & 82 of the GERC (Conduct of Business) Regulations, 2004 seeking extension of time period for construction of the evacuation infrastructure. View PDF