BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T075721Z
LAST-MODIFIED:20260515T075721Z
UID:46096-1780054200-1780074000@gercin.org
SUMMARY:2647/2026
DESCRIPTION:Petition under Electricity Act\, 2003\, for approval to adopt Dry Type Transformers in specific installations and to waive the recovery of incremental loss charges from applicants/developers\, in alignment with modern safety standards\, environmental regulations\, and practices adopted by other distribution licensees.
URL:https://gercin.org/hearing-schedule/2647-2026/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T075801Z
LAST-MODIFIED:20260515T075801Z
UID:46098-1780054200-1780074000@gercin.org
SUMMARY:2652/2026
DESCRIPTION:Petition filed under Section 86(1)(c)\, e) of the Electricity Act\, 2003 read with Regulations 80 and 82 of the GERC (Conduct of Business) Regulations\, 2004 seeking appropriate directions against the imposition of requirement by respondent GETCO to furnish consumer/off-taker details at the stage of application for connectivity\, being contrary to the applicable regulatory framework including the Procedure for Grant of Connectivity dated 04.08.2025 \, Order dated 21.09.2024 passed by the Commission in Petition No. 2377 of 2024\, and the Gujarat Renewable Energy Policy\, 2025\, and for consequential reliefs.
URL:https://gercin.org/hearing-schedule/2652-2026/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T075909Z
LAST-MODIFIED:20260515T075909Z
UID:46102-1780054200-1780074000@gercin.org
SUMMARY:2654/2026 & allied IAs
DESCRIPTION:Petition under Section 86 of the Electricity Act\, 2003 read with Regulation 80 & 82 GERC (Conduct of Business) Regulations\, 2004\, read with Gujarat Renewable Energy Policy\, 2023 & amendments thereof and the Tariff Order dated 31.08.2024 praying before the Commission to exercise its powers under Section 86 of the Electricity Act\, 2003 and direct the Respondent Gujarat Energy Transmission Corporation Limited to grant extension of time for commissioning of the Evacuation Line along with bays and metering system and connectivity of the transmission line and thereby grant\nextension of time in executing the 101 MW Solar Project.
URL:https://gercin.org/hearing-schedule/2654-2026-allied-ias/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T075948Z
LAST-MODIFIED:20260515T075948Z
UID:46104-1780054200-1780074000@gercin.org
SUMMARY:2655/2026 & allied IAs
DESCRIPTION:Petition under Section 86 (1)(f) (c) & (e) and other applicable provisions of the Electricity Act\, 2003 read with read with Regulations 80 & 82 of the GERC (Conduct of Business) Regulations\, 2004 seeking extension of time period for construction of the evacuation infrastructure.
URL:https://gercin.org/hearing-schedule/2655-2026-allied-ias/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T080053Z
LAST-MODIFIED:20260521T125051Z
UID:46183-1780054200-1780074000@gercin.org
SUMMARY:2191/2023
DESCRIPTION:In the matter of Petition under Section 45\, 46\, 86 and other provisions of the Electricity Act\, 2003 read with GERC (Licensee’s Power to Recover Expenditure incurred in providing supply and other Miscellaneous Charges) Regulations\, 2005 for approval of levy of per KVA based charges from\napplicant toward expenditure to be incurred by Distribution Licensee for development of underground electrical network for providing power supply at 11 KV/22 KV voltage level to new HT connection/additional demand.
URL:https://gercin.org/hearing-schedule/2191-2023-4/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T080131Z
LAST-MODIFIED:20260527T112925Z
UID:46277-1780054200-1780074000@gercin.org
SUMMARY:1988/2021 & allied IA
DESCRIPTION:Petition under Section 86 (1) (c)\, (e) and (f) of the Electricity Act\, 2003 read with Clause 3.9 of GERC’s Order No. 06 of 2024 dated 31.08.2024 for extension of commissioning of timelines of 25 MW Solar Plant due to occurrence of circumstances beyond the control of the Petitioner.
URL:https://gercin.org/hearing-schedule/1988-2021-allied-ia-2/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T080232Z
LAST-MODIFIED:20260527T110413Z
UID:46106-1780054200-1780074000@gercin.org
SUMMARY:2648/2026
DESCRIPTION:Petition under Section 86 of the Electricity Act\, 2003 and Order No. 03 of 2022 dated 27.06.2022 issued by the Commission\, seeking approval of Supplemental PPA – 2 signed between the GUVNL and Kedareshwar Khandsari Udyog Pvt. Limited for procurement of additional 2 MW power from Bagasse based Co-generation project for determination of Tariff for Procurement of Power by the Distribution Licensees and Others from Biomass based Power Projects and Bagasse based Co-generation Projects”\, for Control Period from FY 2020-21 to FY 2022-23 in the State of Gujarat.
URL:https://gercin.org/hearing-schedule/2648-2026/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260515T080308Z
LAST-MODIFIED:20260527T110400Z
UID:46108-1780054200-1780074000@gercin.org
SUMMARY:2649/2026 & allied IAs.
DESCRIPTION:Petition under Section 86 of the Electricity Act\, 2003 read with Article 8.1 & 8.2 of the Power Purchase Agreement dated 20.06.2024 executed between M/s Juniper Green Kite Private Limited and Gujarat Urja Vikas Nigam Limited\, seeking extension of the Scheduled Commercial Operation Date of 90 MW Wind Power Project on account of Force Majeure Events.
URL:https://gercin.org/hearing-schedule/2649-2026-allied-ias/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260525T162205Z
LAST-MODIFIED:20260525T162205Z
UID:46220-1780054200-1780074000@gercin.org
SUMMARY:2531/2025 & Allied IA
DESCRIPTION:In the matter of Petition under Section 86(1)(b)\, 86(1)(e)\, Section 86(1)(f) and 86(1)(k) of the\nElectricity Act\, 2003 read with Article 8 of the Power Purchase Agreement dated 10.05.2023\nexecuted between M/s Juniper Green Beam Private Limited and Gujarat Urja Vikas Nigam Limited\,\nfor supply of 50 MW wind power from its project in the state of Gujarat\, seeking inter alia extension of the Scheduled Commercial Operation Date on account of certain Force Majeure events affecting the project implementation and thereby passing appropriate Order(s) / Direction(s) in this regard to the extent prayed for herein.
URL:https://gercin.org/hearing-schedule/2531-2025-allied-ia-4/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260525T162312Z
LAST-MODIFIED:20260525T162312Z
UID:46222-1780054200-1780074000@gercin.org
SUMMARY:2532/2025 & Allied IA
DESCRIPTION:In the matter of Petition under Section 86(1)(b)\, 86(1)(e)\, Section 86(1)(f) and 86(1)(k) of the\nElectricity Act\, 2003 read with Article 8 of the Power Purchase Agreement dated 08.02.2024\nexecuted between M/s Juniper Green Kite Private Limited and Gujarat Urja Vikas Nigam Limited\, for supply of 70 MW wind power from its project in the state of Gujarat\, seeking inter alia extension of the Scheduled Commercial Operation Date on account of certain Force Majeure events affecting the project implementation and thereby passing appropriate Order(s) / Direction(s) in this regard to the extent prayed for herein.
URL:https://gercin.org/hearing-schedule/2532-2025-allied-ia-4/
CATEGORIES:Hearing Schedule
END:VEVENT
BEGIN:VEVENT
DTSTART;TZID=Asia/Kolkata:20260529T113000
DTEND;TZID=Asia/Kolkata:20260529T170000
DTSTAMP:20260608T085113
CREATED:20260525T162530Z
LAST-MODIFIED:20260527T105927Z
UID:46100-1780054200-1780074000@gercin.org
SUMMARY:2653/2026
DESCRIPTION:Petition under Section 86(1)(f) of the Electricity Act\, 2003 read with Electricity (Promotion of Generation of Electricity from Must-Run Power Plant) Rules\, 2021 and the Power Purchase Agreement dated 26.08.2019.